120958RESERVE NOTICE26/11/2024 09:03:43 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 28/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120927 has been updated at 0800 hrs 26/11/2024 to the following:

1. From 1500 hrs to 1600 hrs 28/11/2024.
The forecast capacity reserve requirement is 864 MW.
The minimum capacity reserve available is 611 MW.

2. From 1630 hrs to 1930 hrs 28/11/2024.
The forecast capacity reserve requirement is 826 MW.
The minimum capacity reserve available is 455 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
120957RESERVE NOTICE26/11/2024 09:02:21 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 0530 hrs to 0800 hrs 29/11/2024.
The forecast capacity reserve requirement is 1463 MW.
The minimum capacity reserve available is 1036 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
120956RESERVE NOTICE26/11/2024 09:00:59 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120946 has been updated at 0800 hrs on 26/11/2024 to the following:

From 1430 hrs to 1930 hrs 27/11/2024.
The forecast capacity reserve requirement is 1176 MW.
The minimum capacity reserve available is 25 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
120947RESERVE NOTICE26/11/2024 02:51:23 AM

STPASA - Update to the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 28/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120916 has been updated at 0230 hrs on 26/11/2024 to the following:

[1.] From 0500 hrs 28/11/2024 to 2030 hrs 28/11/2024.
The forecast capacity reserve requirement is 1467 MW.
The minimum capacity reserve available is 26 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
120946RESERVE NOTICE26/11/2024 02:43:59 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120915 has been updated at 0230 hrs on 26/11/2024 to the following:

[1.] From 1300 hrs 27/11/2024 to 2300 hrs 27/11/2024.
The forecast capacity reserve requirement is 1202 MW.
The minimum capacity reserve available is 0 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
120945RESERVE NOTICE26/11/2024 02:33:00 AM

STPASA - Update to the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120917 has been updated at 0230 hrs 26/11/2024 to the following:

[1.] From 1500 hrs 27/11/2024 to 1530 hrs 27/11/2024.
The forecast capacity reserve requirement is 828 MW.
The minimum capacity reserve available is 738 MW.

[2.] From 1730 hrs 27/11/2024 to 2000 hrs 27/11/2024.
The forecast capacity reserve requirement is 792 MW.
The minimum capacity reserve available is 562 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


AEMO Operations
     
120944RESERVE NOTICE26/11/2024 01:55:40 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120911 has been updated at 0130 hrs to the following:

[1.] From 1600 hrs 26/11/2024 to 1900 hrs 26/11/2024.
The forecast capacity reserve requirement is 920 MW.
The minimum capacity reserve available is 451 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
     
120941RESERVE NOTICE25/11/2024 04:50:28 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120911 has been updated at 1645 hrs to the following:

[1.] From 1600 hrs 26/11/2024 to 1900 hrs 26/11/2024.
The forecast capacity reserve requirement is 1105 MW.
The minimum capacity reserve available is 409 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
120927RESERVE NOTICE25/11/2024 03:50:01 PM

STPASA - Update to the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 28/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120918 has been updated at 1500 hrs 25/11/2024 to the following:

From 1630 hrs to 1900 hrs 28/11/2024.
The forecast capacity reserve requirement is 729 MW.
The minimum capacity reserve available is 279 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     