[EventId:198] AP STARTED for ENERGY in NSW1 at 09 May 2024 03:55
Issued by Australian Energy Market Operator Ltd at 0355 hrs on 09 May 2024
ADMINISTERED PRICE PERIOD DECLARED in NSW1 region.
AEMO has determined that the rolling sum of the uncapped spot prices for the NSW1 region over the previous 2016 trading intervals has exceeded the cumulative price threshold (CPT) of $1,490,200.00.
In accordance with Clause 3.14.2(b) of the National Electricity Rules, AEMO has determined that an administered price period will commence at the trading interval starting 0405 hrs on 09 May 2024 and will continue through to the end of that trading day.
An administered price cap (APC) of 600 $/MWh will apply to all trading intervals during this administered price period. This APC will apply to spot prices and to all market ancillary service prices in the NSW1 region.
An administered floor price (AFP) of -600 $/MWh will apply to spot prices.
AEMO will continue to monitor the rolling sum of the uncapped spot prices and issue further Market Notices as required.
This is an AEMO autogenerated Market Notice.
[EventId:197] AP ENDED for ENERGY in NSW1 at 09 May 2024 03:55
Issued by Australian Energy Market Operator Ltd at 0355 hrs on 08 May 2024
ADMINISTERED PRICE PERIOD ENDS in NSW1 region.
In accordance with Clause 3.14.2(b) of the National Electricity Rules, AEMO is notifying market participants that the administered price period declared for the NSW1 region in market notice 116550 will end at 0400 hrs on 09 May 2024.
This is an AEMO autogenerated Market Notice.
[EventId:197] AP STARTED for ENERGY in NSW1 at 08 May 2024 19:45
Issued by Australian Energy Market Operator Ltd at 1945 hrs on 08 May 2024
ADMINISTERED PRICE PERIOD DECLARED in NSW1 region.
AEMO has determined that the rolling sum of the uncapped spot prices for the NSW1 region over the previous 2016 trading intervals has exceeded the cumulative price threshold (CPT) of $1,490,200.00.
In accordance with Clause 3.14.2(b) of the National Electricity Rules, AEMO has determined that an administered price period will commence at the trading interval starting 1955 hrs on 08 May 2024 and will continue through to the end of that trading day.
An administered price cap (APC) of 600 $/MWh will apply to all trading intervals during this administered price period. This APC will apply to spot prices and to all market ancillary service prices in the NSW1 region.
An administered floor price (AFP) of -600 $/MWh will apply to spot prices.
AEMO will continue to monitor the rolling sum of the uncapped spot prices and issue further Market Notices as required.
This is an AEMO autogenerated Market Notice.
Request for Generator Recall Information for 29/02/2024 for QLD Region
Refer to AEMO Electricity Market Notice no. 115193. Additional generation in QLD could assist in alleviating the forecast LOR2 condition in NSW.
Please provide Generator Recall Information for the period 29/02/2024, by 1200 hrs 28/02/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.
SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf
Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf
AEMO Operations
Request for Generator Recall Information for 29/02/2024 for NSW Region
Refer to AEMO Electricity Market Notice no. 115193.
Please provide Generator Recall Information for the period 29/02/2024, by 1200 hrs 28/02/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.
SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf
Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf
AEMO Operations
Load Shedding Direction in the Vic Region
Load Shedding Direction in the Vic Region
AEMO has directed load shedding commencing at 1420 hrs 13/02/2024
in the Victoria region to restore power system security.
The direction was issued under section 116 of the NEL, and was a clause 4.8.9 instruction under the NER.
Manager NEM Real Time Operations
Request for Generator Recall Information for 14/12/2023 for QLD Region
Refer to AEMO Electricity Market Notice no. 112198. Additional generation in QLD could assist in alleviating the forecast LOR condition in NSW.
Please provide Generator Recall Information for the period 14/12/2023, by 1200 hrs on 13/12/2023 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.
SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf
Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf
AEMO Operations
Request for Generator Recall Information for 14/12/2023 for NSW Region
Refer to AEMO Electricity Market Notice no. 112198.
Please provide Generator Recall Information for the period 14/12/2023, by 1200 hrs on 13/12/2023 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.
SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf
Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf
AEMO Operations