Update to system strength requirements in North Queensland
Refer to market notice 106175
AEMO and Powerlink are continuing to investigate system strength requirements in North Queensland.
Due to commissioning of Clarke Creek wind farm in Far North Queensland, the system normal equations have been revised.
A revision to the constraint equations will be implemented at 1100 hrs on Monday 9th December 2024.
The new combinations have now published in a limits advice document on AEMO's website. For more information refer to the new limits advice: https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice
This advice contains all the combinations for Queensland for system normal cases. Additional information has been included in the limit advice to clarify the requirement to disconnect all inverters/turbines under certain system conditions.
The constraint equation in the Q-NIL set of the form below will be modified:
-Q_NIL_STRGTH_KBWF
-Q_NIL_STRGTH_MEWF
Two new equations have been added:
-Q_NIL_STRGTH_CKWF
-Q_NIL_STRGTH_CKWF_I
AEMO Operations
[EventId:202412031750_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 03 December 2024 17:50
Issued by Australian Energy Market Operator Ltd at 1750 hrs on 3 December 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 December 2024.
Refer to market notice: 121435
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1750 hrs on 3 December 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202412031635_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 03 December 2024 16:35
Issued by Australian Energy Market Operator Ltd at 1635 hrs on 3 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1635 hrs on 3 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202412031615_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 03 December 2024 16:15
Issued by Australian Energy Market Operator Ltd at 1615 hrs on 3 December 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 December 2024.
Refer to market notice: 121428
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1615 hrs on 3 December 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202412031510_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 03 December 2024 15:10
Issued by Australian Energy Market Operator Ltd at 1510 hrs on 3 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1510 hrs on 3 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202412031300_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 03 December 2024 13:00
Issued by Australian Energy Market Operator Ltd at 1300 hrs on 3 December 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 December 2024.
Refer to market notice: 121415
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1300 hrs on 3 December 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202412031145_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 03 December 2024 11:45
Issued by Australian Energy Market Operator Ltd at 1145 hrs on 3 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1145 hrs on 3 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
NEM Local Temperature Alerts for SA from 03 Dec 2024 to 07 Dec 2024
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Port Augusta Ap (39+ Deg C): 5th Dec, 6th Dec
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
Cancellation of Actual (LOR1) condition in the NSW region - 02/12/2024
Cancellation of Actual (LOR1) condition in the NSW region - 02/12/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.121384 is cancelled at 1920 hrs 02/12/2024.
Manager NEM Real Time Operations