Market Notices

121236RECLASSIFY CONTINGENCY29/11/2024 01:16:50 PM

Reclassification of a Non-Credible Contingency Event: Ross - Tully South - Woree No.8905 275 kV line line and Cardwell - Tully No.7389 132kV line line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Ross - Tully South - Woree No.8905 275 kV line and Cardwell - Tully No.7389 132kV line

Duration: 29/11/2024 13:16 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
121214RECLASSIFY CONTINGENCY28/11/2024 07:44:16 PM

Cancellation of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV

Cancellation time: 28/11/2024 19:44

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 121145

Auto-generated on behalf of Manager NEM Real Time Operations
     
121204RECLASSIFY CONTINGENCY28/11/2024 07:24:17 PM

Cancellation of a Non-Credible Contingency Event: Bannaby - Mt Piper 5A6 500kV line and Bannaby - Mt Piper 5A7 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Bannaby - Mt Piper 5A6 500kV and Bannaby - Mt Piper 5A7 500kV

Cancellation time: 28/11/2024 19:24

Constraint set(s) revoked:
N-5A6+5A7_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1


Refer AEMO Electricity Market Notice 121144

Auto-generated on behalf of Manager NEM Real Time Operations
     
121189RECLASSIFY CONTINGENCY28/11/2024 06:29:16 PM

Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Cancellation time: 28/11/2024 18:29

Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Refer AEMO Electricity Market Notice 121188

Auto-generated on behalf of Manager NEM Real Time Operations
     
121188RECLASSIFY CONTINGENCY28/11/2024 05:27:47 PM

Reclassification of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Duration: 28/11/2024 17:27 until further notice

Constraint set(s) invoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Auto-generated on behalf of Manager NEM Real Time Operations
     
121169PRICE ADJUSTMENT28/11/2024 02:18:30 PM

[EventId:202411271510_confirmed] Prices for interval 27-Nov-2024 15:10 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1418 hrs on 28 November 2024

PRICES ARE NOW CONFIRMED for trading interval 27-Nov-2024 15:10.

In accordance with Market Notice 121092 AEMO has reviewed this trading interval and determined that:
- Over-Constrained Dispatch has been resolved for this interval

Changed Prices ($/MWh)

TYPE
Region Original Adjusted
Price Price
ENERGY
VIC1 -$30.00 -$29.50
RAISE60SEC
NSW1 $0.10 $0.05
QLD1 $0.10 $0.05
SA1 $0.10 $0.05
VIC1 $0.10 $0.05


This is an AEMO autogenerated Market Notice.
     
121167MARKET INTERVENTION28/11/2024 03:01:25 PM

Cancellation - AEMO Intervention Event - SA region 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 27/11/2024

Refer to Market Notice 121094

The AEMO Intervention Event and all associated directions are cancelled from 1500 hrs on 28/11/2024.


Manager NEM Real Time Operations
     
121166MARKET INTERVENTION28/11/2024 02:59:59 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 121091

Direction is cancelled from: 1500 hrs 28/11/2024

Manager NEM Real Time Operations
     
121165MARKET INTERVENTION28/11/2024 02:29:51 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 121090

Direction is cancelled from: 1430 hrs 28/11/2024

Manager NEM Real Time Operations
     