Filter by category
Filter by Date
Cancellation - MSL1- VIC Region at 1430 hrs 28/09/2024.
Cancellation - MSL1- VIC Region at 1430 hrs 28/09/2024.
Refer to Market Notice 118475.
Manager NEM Real Time Operations
Cancellation - MSL1- VIC Region at 1530 hrs 27/09/2024.
Cancellation - MSL1- VIC Region at 1530 hrs 27/09/2024.
Refer to Market Notice 118442 for MSL1.
Manager NEM Real Time Operations
Minimum System Load 1 (MSL1) in the VIC Region on 28/09/2024
Update to Market Notice 118421.
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1030 hrs to 1430 hrs 28/09/2024.
Minimum regional demand is forecast to be 1420 MW at 1200 hrs, and the advisory threshold is:
- MSL1 - 1865 MW
- MSL2 - 1365 MW
- MSL3 - 865 MW
MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the MSL1 threshold.
Refer to NEM Data Dashboard to monitor demand levels: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/data-dashboard-nem
AEMO is seeking a market response.
An insufficient market response may require AEMO to take action or intervene to maintain power system security in Victoria. This may result in action such as the direction of scheduled production units, curtailment of non-scheduled production units, and/or a direction to maintain regional demand above required MSL threshold, in both Victoria and South Australia.
AEMO Operations
Minimum System Load 1 (MSL1) in the VIC Region on 27/09/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1300 hrs 27/09/2024 to 1330 hrs 27/09/2024.
Minimum regional demand is forecast to be 1879 MW at 1330 hrs, and the advisory threshold is:
o MSL1 - 1915 MW
o MSL2 - 1415 MW
o MSL3 - 915 MW
MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the MSL1 threshold.
Refer to NEM Data Dashboard to monitor demand levels: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/data-dashboard-nem
AEMO is seeking a market response.
An insufficient market response may require AEMO to take action or intervene to maintain power system security in Victoria. This may result in action such as the direction of scheduled production units, curtailment of non-scheduled production units, and/or a direction to maintain regional demand above required MSL threshold, in both Victoria and South Australia.
AEMO Operations
Minimum System Load 1 (MSL1) in the VIC Region on 28/09/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1100 hrs to 1400 hrs 28/09/2024.
Minimum regional demand is forecast to be 1638 MW at 1300 hrs, and the advisory threshold is:
- MSL1 - 1865 MW
- MSL2 - 1365 MW
- MSL3 - 865 MW
MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the MSL1 threshold.
Refer to NEM Data Dashboard to monitor demand levels: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/data-dashboard-nem
AEMO is seeking a market response.
An insufficient market response may require AEMO to take action or intervene to maintain power system security in Victoria. This may result in actions such as recalling network outages, the direction of scheduled production units, curtailment of non-scheduled production units, and/or a direction to maintain regional demand above required MSL threshold, in both Victoria and South Australia.
AEMO Operations
Update - Non-credible contingency event - TAS region - 19/09/2024
Update - Non-credible contingency event - TAS region - 19/09/2024
Refer AEMO Electricity Market Notice 118321
At 1446 hrs the Gordon - Chapel St No 1 and No 2 220 kV lines were returned to service.
This non-credible contingency event was caused by lightning. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Manager NEM Real Time Operations
Update - Non-credible contingency event - TAS region - 19/09/2024
Update - Non-credible contingency event - TAS region - 19/09/2024
At 1340 hrs the Gordon - Chapel St No1 and No 2 220 kV lines tripped.
AEMO did not instruct load shedding.
AEMO has advised of approximately 112 MW disconnection of bulk electrical load,
disconnection of generation at Studland Bay Wind generator (71 MW) and 23 MW generation reduction at Gordon Power station.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Non-credible contingency event - TAS region - 19/09/2024
Non-credible contingency event - TAS region - 19/09/2024
At 1340 hrs the Gordon - Chapel St No1 and No 2 220 kV lines tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Update - Non-credible contingency event - VIC region - 06/09/2024
Update - Non-credible contingency event - VIC region - 06/09/2024
Refer AEMO Electricity Market Notice 118166
At 2005 hrs the Loy Yang PS No. 4 500 kV bus was returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations