Update - Foreseeable AEMO intervention in SA region
Update - Foreseeable AEMO intervention in SA region
Refer AEMO Electricity Market Notice 120476
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2330 hrs 15/11/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
AEMO estimates that, in the absence of sufficient market response by 1445 hrs 15/11/2024, AEMO may need to intervene by issuing a direction.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 14/11/2024
Cancellation - AEMO Intervention Event - SA region 14/11/2024
Refer to Market Notice 120430
The AEMO Intervention Event and all associated directions are cancelled from 1630 hrs on 15/11/2024.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 120432
Direction is cancelled from: 1630 hrs 15/11/2024
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 120444
Direction is cancelled from: 1430 hrs 15/11/2024
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: NSW1
Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV
Duration: 15/11/2024 10:20 until further notice
Constraint set(s) invoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation: Direction issued to: Snowy Hydro Limited - MURR2-2 MURRAY2
Cancellation: Direction issued to: Snowy Hydro Limited - MURR2-2 MURRAY2
Refer to Market Notice 120473
Direction is cancelled from: 0800 hrs 15/11/2024
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2330 hrs 15/11/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB02 JEERALANG B PO
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB02 JEERALANG B PO
Refer AEMO Electricity Participant Notice 120472
The JLB02 JEERALANG B PO direction is now expected to stay in place until 0900 hrs 15/11/2024.
The direction update is issued at 0645 hrs 15/11/2024.
Manager NEM Real Time Operations
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB01 JEERALANG B PO
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB01 JEERALANG B PO
Refer AEMO Electricity Participant Notice 120471
The JLB01 JEERALANG B PO direction is now expected to stay in place until 0900 hrs 15/11/2024.
The direction update is issued at 0645 hrs 15/11/2024.
Manager NEM Real Time Operations