113104RESERVE NOTICE07/01/2024 05:33:14 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 9/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 113081 is cancelled at 1400 hrs 07/01/2024.

No LOR condition is currently forecast in the STPASA period.

Manager NEM Real Time Operations
113082RESERVE NOTICE06/01/2024 02:45:06 PM

STPASA - Update to the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 10/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 113066 has been updated at 1400 hrs 06/01/2024 to the following:

1. From 1730 hrs 10/01/2024 to 1800 hrs 10/01/2024.
The forecast capacity reserve requirement is 1655 MW.
The minimum capacity reserve available is 1565 MW.

Manager NEM Real Time Operations
113081RESERVE NOTICE06/01/2024 02:44:00 PM

STPASA - Update to the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 09/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 113065 has been updated at 1400 hrs 06/01/2024 to the following:

1. From 1500 hrs 09/01/2024 to 1600 hrs 09/01/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1142 MW.

Manager NEM Real Time Operations
113066RESERVE NOTICE05/01/2024 02:57:09 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 10/01/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1730 hrs to 1800 hrs 10/01/2024.
The forecast capacity reserve requirement is 1568 MW.
The minimum capacity reserve available is 1560 MW.

AEMO Operations
113065RESERVE NOTICE05/01/2024 02:56:13 PM

STPASA - Update to the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 09/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 113051 has been updated at 1400 hrs 05/01/2024 to the following:

1. From 1400 hrs to 1600 hrs 09/01/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 721 MW.

2. From 1630 hrs to 1800 hrs 09/01/2024.
The forecast capacity reserve requirement is 1612 MW.
The minimum capacity reserve available is 1258 MW.

AEMO Operations
113051RESERVE NOTICE04/01/2024 03:05:46 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 09/01/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1430 hrs to 1600 hrs 09/01/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1119 MW.

AEMO Operations
112793POWER SYSTEM EVENTS27/12/2023 12:04:43 AM

Non-credible contingency event - QLD region - 26/12/2023

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 26/12/2023

At 2345 hrs the Strathmore Clare South 7208 and the Strathmore Clare South Tee King Creek 7128 132kV lines tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
112627RESERVE NOTICE23/12/2023 02:30:53 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the Qld Region on 29/12/2023

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the Qld region advised in AEMO Electricity Market Notice No.112596 is cancelled at 1430 hrs 23/12/2023.

[No LOR condition is currently forecast in the STPASA period.]

Manager NEM RTO
112596RESERVE NOTICE22/12/2023 03:25:02 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 29/12/2023

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 1830 hrs to 1930 hrs 29/12/2023.
The forecast capacity reserve requirement is 1057 MW.
The minimum capacity reserve available is 1049 MW.