STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 03/06/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1730 hrs to 1830 hrs 03/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1751 MW.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 23/05/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116724 is cancelled at 1400 hrs 21/05/2024.
No LOR condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 22/05/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116723 is cancelled at 1400 hrs 21/05/2024.
No LOR condition is currently forecast in the STPASA period.
AEMO Operations
[EventId:202405201830_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 20 May 2024 18:30
Issued by Australian Energy Market Operator Ltd at 1830 hrs on 20 May 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 20 May 2024.
Refer to market notice: 116731
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1830 hrs on 20 May 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202405201730_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 20 May 2024 17:30
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 20 May 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 20 May 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1730 hrs on 20 May 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 21/05/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116722 for the 21/05/2024 is cancelled at 1600 hrs 20/05/2024.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/05/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No.116700 has been updated at 1450 hrs to the following:
[1.] From 1630 hrs 20/05/2024 to 1900 hrs 20/05/2024.
The forecast capacity reserve requirement is 1630 MW.
The minimum capacity reserve available is 958 MW.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 23/05/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 0000 hrs to 0130 hrs 23/05/2024.
The forecast capacity reserve requirement is 1640 MW.
The minimum capacity reserve available is 1422 MW.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 22/05/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116703 has been updated at 1400 hrs 20/05/2024 to the following:
1. From 0600 hrs to 0800 hrs 22/05/2024.
The forecast capacity reserve requirement is 1630 MW.
The minimum capacity reserve available is 1386 MW.
2. From 1630 hrs to 2359 hrs 22/05/2024.
The forecast capacity reserve requirement is 1610 MW.
The minimum capacity reserve available is 1337 MW.
AEMO Operations