Filter by category
Filter by Date
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region beginning on 08/05/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
From 0500 hrs to 0830 hrs 08/05/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1265 MW.
From 1530 hrs to 2359 hrs 08/05/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1252 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region beginning on 07/05/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
From 1700 hrs to 1800 hrs 07/05/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1355 MW.
AEMO Operations.
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 02/05/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1700 hrs 02/05/2024 to 1830 hrs 02/05/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1390 MW.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Monday, 29 April 2024
NON-CONFORMANCE NSW1 Region Monday, 29 April 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP5
Duration: 29/04/2024 20:50 to 29/04/2024 20:55
Amount: -18 MW
Constraint: NC-N_VP5
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Monday, 29 April 2024
NON-CONFORMANCE VIC1 Region Monday, 29 April 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: JLB01
Duration: 29/04/2024 13:00 to 29/04/2024 13:05
Amount: 35 MW
Constraint: NC-V_JLB01
Auto-generated on behalf of Manager NEM Real Time Operations
Inter-regional transfer limit variation - Dapto - Marulan No. 8 330 kV Line - NSW region - 27/04/2024
Inter-regional transfer limit variation - Dapto - Marulan No. 8 330 kV Line - NSW region - 27/04/2024
At 0830 hrs 27/04/2024 there was a short notice outage of Dapto - Marulan No. 8 330 kV Line.
Constraint set(s) invoked: N-DTMN_8_15M
This constraint set contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Friday, 26 April 2024
NON-CONFORMANCE VIC1 Region Friday, 26 April 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: YWPS3
Duration: 26/04/2024 22:40 to 26/04/2024 22:45
Amount: 17 MW
Constraint: NC-V_YWPS3
Auto-generated on behalf of Manager NEM Real Time Operations
Inter-regional transfer limit variation - Para No 1 SVC - SA region - 23/04/2024
Inter-regional transfer limit variation - Para No 1 SVC - SA region - 23/04/2024
At 0837 hrs 23/04/2024 there was an unplanned outage of Para No 1 SVC.
Constraint set(s) invoked: S-PA_VC1
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA,V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation -Liddell - Tomago 82 330kV Line - NSW region - 22/04/2024
Inter-regional transfer limit variation - Liddell - Tomago 82 330kV Line - NSW region - 22/04/2024
A planned outage of Liddell - Tomago 82 330kV Line in the NSW region was scheduled from 0600 hrs 03/04/2024 to 1700 hrs 22/04/2024.
The outage has been completed and Liddell - Tomago 82 330kV Line returned to service at 1450 hrs 22/04/2024
Constraint set(s) revoked: N-LDTM_82_OPEN
Manager NEM Real Time Operations