Market Notices

114881SETTLEMENTS RESIDUE19/02/2024 03:15:26 PM

[EventId:202402191515_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 19 February 2024 15:15

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1515 hrs on 19 February 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 19 February 2024.

Refer to market notice: 114879

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1515 hrs on 19 February 2024.

This is an AEMO autogenerated Market Notice.
114879SETTLEMENTS RESIDUE19/02/2024 02:05:15 PM

[EventId:202402191405_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 19 February 2024 14:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1405 hrs on 19 February 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 19 February 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1405 hrs on 19 February 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
114876SETTLEMENTS RESIDUE19/02/2024 12:00:28 PM

[EventId:202402191200_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 19 February 2024 12:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1200 hrs on 19 February 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 19 February 2024.

Refer to market notice: 114873

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1200 hrs on 19 February 2024.

This is an AEMO autogenerated Market Notice.
114873SETTLEMENTS RESIDUE19/02/2024 10:35:33 AM

[EventId:202402191035_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 19 February 2024 10:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1035 hrs on 19 February 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 19 February 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1035 hrs on 19 February 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
114863NON-CONFORMANCE18/02/2024 03:15:21 PM

NON-CONFORMANCE Region NSW1 Sunday, 18 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Sunday, 18 February 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: DPNTBG1, DPNTBL1
Aggregate Dispatch Group: DPNTBESS_ADG1
Duration: 18/02/2024 14:55 to 18/02/2024 15:15
Amount: 21 MW
Constraint: NC-N_DPNTBESS_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
114840NON-CONFORMANCE17/02/2024 03:35:16 PM

NON-CONFORMANCE Region QLD1 Saturday, 17 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Saturday, 17 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 17/02/2024 15:25 to 17/02/2024 15:35
Amount: -19 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
114780NON-CONFORMANCE16/02/2024 01:25:13 AM

NON-CONFORMANCE Region NSW1 Friday, 16 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Friday, 16 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BW04
Duration: 16/02/2024 01:15 to 16/02/2024 01:25
Amount: 58 MW
Constraint: NC-N_BW04

Auto-generated on behalf of Manager NEM Real Time Operations
114765NON-CONFORMANCE15/02/2024 04:20:12 PM

NON-CONFORMANCE Region QLD1 Thursday, 15 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 15 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: SWAN_E
Duration: 15/02/2024 16:05 to 15/02/2024 16:20
Amount: -46 MW
Constraint: NC-Q_SWAN_E

Auto-generated on behalf of Manager NEM Real Time Operations
114759POWER SYSTEM EVENTS15/02/2024 02:06:23 PM

Update: Significant power system event - Victoria Region - Hazelwood transformers and Hazelwood PS - Jeeralang No 2 220kV -13/02/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Significant power system event - 13/02/2024

Refer AEMO Electricity Market Notices 114685

At 1247 hrs 15/02/2024 the Hazelwood PS - Jeeralang No 2 220kV line was returned to service in the Victoria region

All of the equipment has now been returned to service.

The cause of this significant power system event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations