Filter by category
Filter by Date
CHG0082511 | Pre-Production | Pre-Prod MSATS 50.0.4 LCCD Defect Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Pre-Prod MSATS 50.0.4 LCCD Defect Release
Change Start Date & Time: 09/01/2024 13:00:00 AEST
Change End Date & Time: 09/01/2024 17:00:00 AEST
Outage Start Date & Time: 09/01/2024 13:00:00 AEST
Outage End Date & Time: 09/01/2024 15:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
CHG0082504 | Pre-Production | Removal of support of TLS Version 1.1 and lower
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Market Network
Change Title: Removal of support of TLS Version 1.1 and lower
Change Start Date & Time: 14/02/2024 10:00:00 AEST
Change End Date & Time: 14/02/2024 14:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Pre-Production
Participant Impact and Requirements: Participants using TLS version 1.1 and lower, need to update their servers to use TLSv1.2 as a minimum. Failing to do so would impact the connectivity with AEMO. An outage is not expected but, there may be some minor interruptions during the change period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 19/12/2023
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112483 is cancelled at 1100 hrs 18/12/2023.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Update to the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 19/12/2023
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112471 has been updated at 0500 hrs 18/12/2023 to the following:
From 1230 hrs 19/12/2023 to 1600 hrs 19/12/2023.
The forecast capacity reserve requirement is 1071 MW.
The minimum capacity reserve available is 42 MW.
AEMO is seeking a market response.
AEMO estimates that the latest time at which permission can be given for a planned outage to proceed is 0530 hrs on 19/12/2023.
Manager NEM RTO
STPASA - Update to the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 19/12/2023
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112427 has been updated at 1515 hrs 17/12/2023 to the following:
From 1230 hrs 19/12/2023 to 1600 hrs 19/12/2023.
The forecast capacity reserve requirement is 1346 MW.
The minimum capacity reserve available is 205 MW.
AEMO is seeking a market response.
AEMO estimates that the latest time at which permission can be given for a planned outage to proceed is 0530 hrs on 19/12/2023.
Manager NEM RTO
STPASA - Update to the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 19/12/2023
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112392 has been updated at 1530 hrs 16/12/2023 to the following:
From 1330 hrs to 1600 hrs 19/12/2023.
The forecast capacity reserve requirement is 685 MW.
The minimum capacity reserve available is 128 MW.
AEMO is seeking a market response.
AEMO estimates that the latest time at which permission can be given for a planned outage to proceed is 0530 hrs on 19/12/2023.
Manager NEM RTO
STPASA - Update to the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 19/12/2023
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112390 has been updated at 1600 hrs 15/12/2023 to the following:
From 1430 hrs to 1600 hrs 19/12/2023.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 171 MW.
AEMO is seeking a market response.
AEMO estimates that the latest time at which permission can be given for a planned outage to proceed is 0530 hrs on 19/12/2023.
AEMO Operations
STPASA - Update to the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 19/12/2023
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112371 has been updated at 1500 hrs 15/12/2023 to the following:
From 1430 hrs to 1600 hrs 19/12/2023.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 273 MW.
AEMO is seeking a market response.
AEMO estimates that the latest time at which permission can be given for a planned outage to proceed is 0530 hrs on 19/12/2013.
AEMO Operations
STPASA - Update to the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 19/12/2023
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112317 has been updated at 0900 hrs 15/12/2023 to the following:
From 1430 hrs to 1600 hrs 19/12/2023.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 232 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations