Market Notices

120004SETTLEMENTS RESIDUE06/11/2024 03:21:45 PM

[EventId:202411061520_NRM_SA1_VIC1_stopped] NEGRES CONSTRAINT NRM_SA1_VIC1 ceased operating from 06 November 2024 15:20

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1520 hrs on 6 November 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 6 November 2024.

Refer to market notice: 119986

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the SA to VIC directional interconnector.

The negative residue constraint NRM_SA1_VIC1 ceased operating at 1520 hrs on 6 November 2024.

This is an AEMO autogenerated Market Notice.
     
119994SETTLEMENTS RESIDUE06/11/2024 02:47:19 PM

[EventId:202411061445_NRM_VIC1_NSW1_stopped] NEGRES CONSTRAINT NRM_VIC1_NSW1 ceased operating from 06 November 2024 14:45

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1445 hrs on 6 November 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 6 November 2024.

Refer to market notice: 119973

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to NSW directional interconnector.

The negative residue constraint NRM_VIC1_NSW1 ceased operating at 1445 hrs on 6 November 2024.

This is an AEMO autogenerated Market Notice.
     
119986SETTLEMENTS RESIDUE06/11/2024 02:36:33 PM

[EventId:202411061435_NRM_SA1_VIC1_started] NEGRES CONSTRAINT NRM_SA1_VIC1 started operating from 06 November 2024 14:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1435 hrs on 6 November 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 6 November 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the SA to VIC directional interconnector.

The negative residue constraint set NRM_SA1_VIC1 commenced operating from 1435 hrs on 6 November 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
119973SETTLEMENTS RESIDUE06/11/2024 02:05:18 PM

[EventId:202411061405_NRM_VIC1_NSW1_started] NEGRES CONSTRAINT NRM_VIC1_NSW1 started operating from 06 November 2024 14:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1405 hrs on 6 November 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 6 November 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to NSW directional interconnector.

The negative residue constraint set NRM_VIC1_NSW1 commenced operating from 1405 hrs on 6 November 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
119963GENERAL NOTICE06/11/2024 11:27:15 AM

Correction to testing time for Project Energy Connect (PEC-1) 6th November 2024 for flows in both directions

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 119961

This is correction to Project Energy Connect (PEC-1) testing time issued in previous notice 119961.
Testing time is on 6th November from 11:00 hrs to 22:00 hrs.

The test is for flows in both directions up to 50 MW. This test includes a trip and reclose of a line in South Australia. Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.

Mya San
AEMO Operations
     
119961GENERAL NOTICE06/11/2024 10:03:46 AM

Revised testing time for Project Energy Connect (PEC-1) 6th November 2024 for flows in both directions

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 119901

The Project Energy Connect (PEC-1) testing opportunity has changed ans it is now on 6th November at 22:00 hrs.

The test is for flows in both directions up to 50 MW.

This test includes a trip and reclose of a line in South Australia.

Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.

Terry Liu
AEMO Operations
     
119946SETTLEMENTS RESIDUE06/11/2024 08:45:21 AM

[EventId:202411060845_NRM_SA1_VIC1_stopped] NEGRES CONSTRAINT NRM_SA1_VIC1 ceased operating from 06 November 2024 08:45

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0845 hrs on 6 November 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 6 November 2024.

Refer to market notice: 119942

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the SA to VIC directional interconnector.

The negative residue constraint NRM_SA1_VIC1 ceased operating at 0845 hrs on 6 November 2024.

This is an AEMO autogenerated Market Notice.
     
119942SETTLEMENTS RESIDUE06/11/2024 08:05:21 AM

[EventId:202411060805_NRM_SA1_VIC1_started] NEGRES CONSTRAINT NRM_SA1_VIC1 started operating from 06 November 2024 08:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0805 hrs on 6 November 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 6 November 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the SA to VIC directional interconnector.

The negative residue constraint set NRM_SA1_VIC1 commenced operating from 0805 hrs on 6 November 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
119915SETTLEMENTS RESIDUE05/11/2024 02:00:26 PM

[EventId:202411051400_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 05 November 2024 14:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1400 hrs on 5 November 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 5 November 2024.

Refer to market notice: 119914

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1400 hrs on 5 November 2024.

This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm