Filter by category
Filter by Date
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 10/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1830 hrs 10/12/2024 to 1900 hrs 10/12/2024.
The forecast capacity reserve requirement is 1320 MW.
The minimum capacity reserve available is 1197 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region beginning on 10/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121698 is cancelled at 1745 hrs 10/12/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 10/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1830 hrs 10/12/2024 to 1900 hrs 10/12/2024.
The forecast capacity reserve requirement is 1385 MW.
The minimum capacity reserve available is 1336 MW.
Manager NEM Real Time Operations
CHG0100201 | Production | Planned maintenance affecting the AEMO Market Network
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MarketNet
Change Title: Planned maintenance affecting the AEMO Market Network.
Change Start Date & Time: 16/12/2024 08:00:00 AEST
Change End Date & Time: 17/12/2024 17:00:00 AEST
Outage Start Date & Time: 16/12/2024 15:12:00 AEST
Outage End Date & Time: 16/12/2024 15:13:00 AEST
Environment: Production
Participant Impact and Requirements: Planned maintenance will be conducted on the 16th of December 2024, between 07:30AM and 05:00PM AEST on the core network infrastructure within the AEMO Market Network in Brisbane.
During there change, there will be two instances of 1-3 second service disruption to MarketNet Services accessed via Brisbane as traffic moves from the active to the standby load balancing unit. All Services should return to normal after this time. Traffic via Sydney will not be affected during this time. AEMO recommends that all market participants with site to site VPN connections currently connected via Brisbane, to switch these connections to the Sydney site as a precaution.
Participants connecting via IPWAN and/or SSL VPN will be automatically connected to the Sydney site and do not need to take any action.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 17/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
1. From 1700 hrs to 1830 hrs 17/12/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1310 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
1. From 1500 hrs 16/12/2024 to 1630 hrs 16/12/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.
2. From 1930 hrs to 2030 hrs 16/12/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 962 MW.
AEMO Operations
CHG0100257 | Production | MarketNet Services via Brisbane service disruption for 1-3 seconds as traffic is failed between highly available load balancing services
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Local Area Network
Change Title: MarketNet Services via Brisbane service disruption for 1-3 seconds as traffic is failed between highly available load balancing services.
Change Start Date & Time: 12/12/2024 14:00:00 AEST
Change End Date & Time: 12/12/2024 16:00:00 AEST
Outage Start Date & Time: 12/12/2024 15:00:00 AEST
Outage End Date & Time: 12/12/2024 15:01:00 AEST
Environment: Production
Participant Impact and Requirements: During there change, there will be a 1-3 second service disruption to MarketNet Services accessed via Brisbane as traffic moves from the active to the standby load balancing unit. All Services should return to normal after this time. Traffic via Norwest will not be affected during this time.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
[EventId:202412091800_review] Prices for interval 09-Dec-2024 18:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1755 hrs on 9 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 09-Dec-2024 18:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412091755_review] Prices for interval 09-Dec-2024 17:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1750 hrs on 9 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 09-Dec-2024 17:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.