Filter by category
Filter by Date
Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS
Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer AEMO Electricity Participant Notice 120529
The MINTARO MINTARO GAS direction is now expected to stay in place until 1830 hrs 18/11/2024.
The direction update is issued at 1600 hrs 17/11/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 120528
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 19/11/2024.
The direction update is issued at 1600 hrs 17/11/2024.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Armidale to Dumaresq (8C) 330 kV line - NSW region - 17/11/2024
Inter-regional transfer limit variation - Armidale to Dumaresq (8C) 330 kV line - NSW region - 17/11/2024
A planned outage of Armidale to Dumaresq (8C) 330 kV line in the NSW region was scheduled from 0500 hrs 17/11/2024 to 1700 hrs 17/11/2024.
The outage has been completed returned to service at 1330 hrs 17/11/2024
Constraint set(s) revoked:
N-ARDM_8C
N-DM_SVC
N-TW_SVC
N-X_8C+DM+TW_SVC
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 18/11/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1800 hrs 18/11/2024 to 1900 hrs 18/11/2024.
The forecast capacity reserve requirement is 633 MW.
The minimum capacity reserve available is 484 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 18/11/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 18/11/2024 to 1930 hrs 18/11/2024.
The forecast capacity reserve requirement is 867MW.
The minimum capacity reserve available is 484 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 120527
Direction is cancelled from: 1700 hrs 16/11/2024
Manager NEM Real Time Operations
Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS
Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer to Market Notice 120499
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Synergen Power Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS at 1600 hrs 16/11/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0100 hrs 17/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 18/11/2024.
Synergen Power Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 120500
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 18/11/2024.
The direction update is issued at 1600 hrs 16/11/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 120498
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1700 hrs 16/11/2024.
The direction update is issued at 1440 hrs 16/11/2024.
Manager NEM Real Time Operations