Market Notices

118493MINIMUM SYSTEM LOAD28/09/2024 02:30:26 PM

Cancellation - MSL1- VIC Region at 1430 hrs 28/09/2024.

AEMO ELECTRICITY MARKET NOTICE

Cancellation - MSL1- VIC Region at 1430 hrs 28/09/2024.
Refer to Market Notice 118475.

Manager NEM Real Time Operations
     
118489GENERAL NOTICE27/09/2024 09:51:41 PM

Network Augmentation Commissioned - NSW Region - 27/09/2024

AEMO ELECTRICITY MARKET NOTICE

A network augmentation has been commissioned in the NSW region at 2150 hrs 27/09/2024 as follows:

Walla Walla substation has been cut into the existing Wagga - Jinderra (62) 330 kV line to form the following circuits:

Jinderra - Walla Walla 62 330 kV Transmission Line
Walla Walla - Wagga 6Y 330 kV Transmission Line

Manager NEM Real Time Operations
     
118483MINIMUM SYSTEM LOAD27/09/2024 03:35:11 PM

Cancellation - MSL1- VIC Region at 1530 hrs 27/09/2024.

AEMO ELECTRICITY MARKET NOTICE
Cancellation - MSL1- VIC Region at 1530 hrs 27/09/2024.
Refer to Market Notice 118442 for MSL1.
Manager NEM Real Time Operations
     
118475MINIMUM SYSTEM LOAD27/09/2024 10:55:57 AM

Minimum System Load 1 (MSL1) in the VIC Region on 28/09/2024

AEMO ELECTRICITY MARKET NOTICE

Update to Market Notice 118421.

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1030 hrs to 1430 hrs 28/09/2024.

Minimum regional demand is forecast to be 1420 MW at 1200 hrs, and the advisory threshold is:
- MSL1 - 1865 MW
- MSL2 - 1365 MW
- MSL3 - 865 MW

MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the MSL1 threshold.

Refer to NEM Data Dashboard to monitor demand levels: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/data-dashboard-nem

AEMO is seeking a market response.

An insufficient market response may require AEMO to take action or intervene to maintain power system security in Victoria. This may result in action such as the direction of scheduled production units, curtailment of non-scheduled production units, and/or a direction to maintain regional demand above required MSL threshold, in both Victoria and South Australia.

AEMO Operations
     
118442MINIMUM SYSTEM LOAD25/09/2024 03:14:36 PM

Minimum System Load 1 (MSL1) in the VIC Region on 27/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1300 hrs 27/09/2024 to 1330 hrs 27/09/2024.

Minimum regional demand is forecast to be 1879 MW at 1330 hrs, and the advisory threshold is:
o MSL1 - 1915 MW
o MSL2 - 1415 MW
o MSL3 - 915 MW

MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the MSL1 threshold.

Refer to NEM Data Dashboard to monitor demand levels: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/data-dashboard-nem

AEMO is seeking a market response.

An insufficient market response may require AEMO to take action or intervene to maintain power system security in Victoria. This may result in action such as the direction of scheduled production units, curtailment of non-scheduled production units, and/or a direction to maintain regional demand above required MSL threshold, in both Victoria and South Australia.

AEMO Operations
     
118427GENERAL NOTICE24/09/2024 03:38:49 PM

Network Augmentation Commissioned - NSW Region - 24/09/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - NSW Region - 24/09/2024

At 1535 hrs Buronga - Redcliffs X1 220 kV line has been commissioned.


Manager NEM Real Time Operations
     
118421MINIMUM SYSTEM LOAD24/09/2024 02:54:54 PM

Minimum System Load 1 (MSL1) in the VIC Region on 28/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1100 hrs to 1400 hrs 28/09/2024.
Minimum regional demand is forecast to be 1638 MW at 1300 hrs, and the advisory threshold is:
- MSL1 - 1865 MW
- MSL2 - 1365 MW
- MSL3 - 865 MW

MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the MSL1 threshold.

Refer to NEM Data Dashboard to monitor demand levels: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/data-dashboard-nem

AEMO is seeking a market response.

An insufficient market response may require AEMO to take action or intervene to maintain power system security in Victoria. This may result in actions such as recalling network outages, the direction of scheduled production units, curtailment of non-scheduled production units, and/or a direction to maintain regional demand above required MSL threshold, in both Victoria and South Australia.

AEMO Operations
     
118342GENERAL NOTICE20/09/2024 04:43:35 PM

Update - Lightning vulnerable lines in TAS region

AEMO ELECTRICITY MARKET NOTICE.

Update - Lightning vulnerable lines in TAS region

Refer to AEMO Electricity Market Notice 118320 ,118321, 118322

At 1340 hrs 19/09/2024 the Gordon - Chapel St No 1 220 kV line and the Gordon - Chapel St No 2 220 kV line tripped.
The cause of the trip was identified as due to Lightning.

In accordance with SO_OP_3715, AEMO now considers the Gordon - Chapel St No 1 220 kV line and the Gordon - Chapel St No 2 220 kV line to be vulnerable with a category of Vulnerability due to Lightning.

Manager NEM Real Time Operations
     
118323CONSTRAINTS19/09/2024 04:20:22 PM

Update to system normal constraint equation in NSW for transient voltage stability in south-west NSW

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 92840.

Transgrid has advised AEMO of an update to the transient voltage stability limit in south-west NSW for loss of Darlington Point to Wagga (63) 330 kV line. The limit will include terms for the Darlington Point and Riverina BESS.

The following constraint equation will be updated with the above changes at 1100 hrs Friday 20th September 2024.
N::N_NIL_63

For full details on the formulation, the new constraint equation has now been loaded into AEMO's pre-production systems.

For further details on these constraint equation please contact ben.blake@aemo.com.au

Ben Blake
AEMO Operations
     
X