Market Notices

121166MARKET INTERVENTION28/11/2024 02:59:59 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 121091

Direction is cancelled from: 1500 hrs 28/11/2024

Manager NEM Real Time Operations
     
121165MARKET INTERVENTION28/11/2024 02:29:51 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 121090

Direction is cancelled from: 1430 hrs 28/11/2024

Manager NEM Real Time Operations
     
121157PRICES SUBJECT TO REVIEW28/11/2024 01:40:23 PM

[EventId:202411281345_review] Prices for interval 28-Nov-2024 13:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1340 hrs on 28 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 28-Nov-2024 13:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121156PRICES SUBJECT TO REVIEW28/11/2024 01:35:16 PM

[EventId:202411281340_review] Prices for interval 28-Nov-2024 13:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1335 hrs on 28 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 28-Nov-2024 13:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121154PRICES SUBJECT TO REVIEW28/11/2024 01:30:27 PM

[EventId:202411281335_review] Prices for interval 28-Nov-2024 13:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 28 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 28-Nov-2024 13:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121153PRICES SUBJECT TO REVIEW28/11/2024 01:25:16 PM

[EventId:202411281330_review] Prices for interval 28-Nov-2024 13:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1325 hrs on 28 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 28-Nov-2024 13:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121152PRICES SUBJECT TO REVIEW28/11/2024 01:20:21 PM

[EventId:202411281325_review] Prices for interval 28-Nov-2024 13:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1320 hrs on 28 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 28-Nov-2024 13:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121149PRICES SUBJECT TO REVIEW28/11/2024 01:15:19 PM

[EventId:202411281320_review] Prices for interval 28-Nov-2024 13:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1315 hrs on 28 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 28-Nov-2024 13:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121145RECLASSIFY CONTINGENCY28/11/2024 11:42:55 AM

Reclassification of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV

Duration: 28/11/2024 11:42 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm