117487POWER SYSTEM EVENTS27/07/2024 10:52:18 AM

Correction - Non-credible contingency event - QLD region - 27/07/2024

AEMO ELECTRICITY MARKET NOTICE.

Correction to Market Notice 117486

Non-credible contingency event - QLD region - 27/07/2024

At 0951 hrs the H38 Goodna No. 2 275kV Bus and the H38 Goodna No. 1 275/132kV transformer tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
117486POWER SYSTEM EVENTS27/07/2024 10:26:53 AM

Non-credible contingency event - QLD region - 27/07/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 27/07/2024

At 0951 hrs the H3 Goodna No. 2 275kV Bus and the H3 Goodna No. 1 275/132kV transformer tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
117210POWER SYSTEM EVENTS27/06/2024 09:01:59 AM

Non-credible contingency event - NSW region - 27/06/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - NSW region - 27/06/2024

At 0845 hrs the Sydney West No.1 330 kV SVC tripped during switching for planned outage of Sydney West No.4 330/132 kV transformer.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
117132POWER SYSTEM EVENTS25/06/2024 10:20:35 AM

Non-credible contingency event - NSW region - 25/06/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - NSW region - 25/06/2024

At 0901 hrs the Sydney West No.1 330 kV SVC tripped during switching for planned outage of Sydney West No.4 330/132 kV transformer.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
117042POWER SYSTEM EVENTS18/06/2024 10:16:34 AM

Non-credible contingency event - VIC region - 18/06/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - VIC region - 18/06/2024

At 0839 hrs the Glenrowan No1 66kV Bus tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations