Market Notices

114929RESERVE NOTICE21/02/2024 07:22:43 PM

Update - Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 21/02/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 21/02/2024

Refer AEMO Electricity Market Notice 114927

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 1900 hrs.
The Actual LOR1 condition is not forecast in Pre Dispatch

The capacity reserve requirement is 428 MW
The minimum capacity reserve available is 277 MW

Manager NEM Real Time Operations
114927RESERVE NOTICE21/02/2024 06:47:19 PM

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 21/02/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 21/02/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 1830 hrs.
The Actual LOR1 condition is not forecast in Pre Dispatch

The capacity reserve requirement is 431 MW
The minimum capacity reserve available is 414 MW

Manager NEM Real Time Operations
114632RESERVE NOTICE13/02/2024 03:19:41 PM

Cancellation of Actual (LOR3) condition in the VIC region - 13/02/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR3) condition in the VIC region - 13/02/2024

The Actual LOR3 Condition in the VIC region advised in AEMO Electricity Market Notice No.114604 is cancelled at 1515 hrs 13/02/2024.

Manager NEM Real Time Operations
114604RESERVE NOTICE13/02/2024 02:27:41 PM

Actual Lack Of Reserve Level 3 (LOR3) in the VIC region - 13/02/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 3 (LOR3) in the VIC region - 13/02/2024

Customer load shedding of non-interruptible load is occurring in the VIC region as a result of a shortfall of available capacity reserves.

An Actual LOR3 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the VIC region from 1420 hrs.
The Actual LOR3 condition is not forecast in Pre Dispatch.

The maximum load to be interrupted is up to 450 MW from 1420 hrs 13/02/2024

Manager NEM Real Time Operations
114401RESERVE NOTICE06/02/2024 07:43:29 PM

Cancellation of Actual (LOR1) condition in the QLD region - 06/02/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 06/02/2024

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.114399 is cancelled at 1945 hrs 06/02/2024.

Manager NEM Real Time Operations
114399RESERVE NOTICE06/02/2024 07:22:16 PM

Update - Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 06/02/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 06/02/2024

The actual LOR1 condition in the Qld region advised in AEMO Electricity Market Notice No. 114397 has been updated at 1915 hrs 06/02/2024 to the following:

The Actual LOR1 condition is forecast to exist until 2000 hrs.

The forecast capacity reserve requirement is 1045 MW.
The minimum capacity reserve available is 950 MW.

Manager NEM Real Time Operations
114397RESERVE NOTICE06/02/2024 06:08:41 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 06/02/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 06/02/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs

The capacity reserve requirement is 1095 MW
The minimum capacity reserve available is 892 MW

Manager NEM Real Time Operations
113998RESERVE NOTICE29/01/2024 08:23:46 PM

Cancellation of Actual (LOR1) condition in the QLD region - 29/01/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 29/01/2024

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.113994 is cancelled at 2000 hrs 29/01/2024.

Manager NEM Real Time Operations
113994RESERVE NOTICE29/01/2024 06:12:37 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 29/01/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 29/01/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1810 hrs.

The Actual LOR1 condition is forecast to exist until 1900 hrs.

The forecast capacity reserve requirement is 1197 MW.
The minimum capacity reserve available is 1026 MW.

Manager NEM Real Time Operations