Market Notices

112959SETTLEMENTS RESIDUE01/01/2024 10:30:28 AM

[EventId:202401011030_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 01 January 2024 10:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1030 hrs on 1 January 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 1 January 2024.

Refer to market notice: 112958

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1030 hrs on 1 January 2024.

This is an AEMO autogenerated Market Notice.
112958SETTLEMENTS RESIDUE01/01/2024 09:35:15 AM

[EventId:202401010935_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 01 January 2024 09:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0935 hrs on 1 January 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 1 January 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0935 hrs on 1 January 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
112938SETTLEMENTS RESIDUE31/12/2023 11:00:27 AM

[EventId:202312311100_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 31 December 2023 11:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1100 hrs on 31 December 2023

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 31 December 2023.

Refer to market notice: 112935

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1100 hrs on 31 December 2023.

This is an AEMO autogenerated Market Notice.
112937NON-CONFORMANCE31/12/2023 10:45:13 AM

NON-CONFORMANCE Region VIC1 Sunday, 31 December 2023

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Sunday, 31 December 2023

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: GANNSF1
Duration: 31/12/2023 10:25 to 31/12/2023 10:45
Amount: 25 MW
Constraint: NC-V_GANNSF1

Auto-generated on behalf of Manager NEM Real Time Operations
112935SETTLEMENTS RESIDUE31/12/2023 10:05:26 AM

[EventId:202312311005_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 31 December 2023 10:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1005 hrs on 31 December 2023

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 31 December 2023.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1005 hrs on 31 December 2023.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
112923SETTLEMENTS RESIDUE30/12/2023 04:00:27 PM

[EventId:202312301600_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 30 December 2023 16:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1600 hrs on 30 December 2023

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 30 December 2023.

Refer to market notice: 112921

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1600 hrs on 30 December 2023.

This is an AEMO autogenerated Market Notice.
112921SETTLEMENTS RESIDUE30/12/2023 03:05:26 PM

[EventId:202312301505_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 30 December 2023 15:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1505 hrs on 30 December 2023

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 30 December 2023.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1505 hrs on 30 December 2023.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
112918SETTLEMENTS RESIDUE30/12/2023 02:00:21 PM

[EventId:202312301400_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 30 December 2023 14:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1400 hrs on 30 December 2023

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 30 December 2023.

Refer to market notice: 112915

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1400 hrs on 30 December 2023.

This is an AEMO autogenerated Market Notice.
112916NON-CONFORMANCE30/12/2023 01:05:12 PM

NON-CONFORMANCE Region NSW1 Saturday, 30 December 2023

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Saturday, 30 December 2023

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: NEWENSF2
Duration: 30/12/2023 12:50 to 30/12/2023 13:05
Amount: 163 MW
Constraint: NC-N_NEWENSF2

Auto-generated on behalf of Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm