Market Notices

113351NON-CONFORMANCE17/01/2024 09:10:55 AM

NON-CONFORMANCE Region QLD1 Wednesday, 17 January 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 17 January 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 17/01/2024 09:05 to 17/01/2024 09:10
Amount: -149 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
113346RESERVE NOTICE17/01/2024 06:30:49 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 19/01/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

[1.] From 1530 hrs 19/01/2024 to 1600 hrs 19/01/2024.
The forecast capacity reserve requirement is 696 MW.
The minimum capacity reserve available is 677 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
113341RESERVE NOTICE17/01/2024 04:35:14 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 19/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice 113337 is cancelled at 0430 hrs 17/01/2024.

No LOR2 condition is currently forecast in the STPASA period.

Manager NEM Real Time Operations
113337RESERVE NOTICE17/01/2024 01:39:36 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 19/01/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

[1.] From 1500 hrs 19/01/2024 to 1600 hrs 19/01/2024.
The forecast capacity reserve requirement is 708 MW.
The minimum capacity reserve available is 671 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
113305RESERVE NOTICE16/01/2024 08:35:09 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 18/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113285 is cancelled at 0700 hrs 16/01/2024.

No LOR2 condition is currently forecast in the STPASA period.

AEMO Operations
113285RESERVE NOTICE15/01/2024 09:27:44 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 18/01/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

[1.] From 1730 hrs 18/01/2024 to 2030 hrs 18/01/2024.
The forecast capacity reserve requirement is 870 MW.
The minimum capacity reserve available is 681 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
113172NON-CONFORMANCE10/01/2024 12:30:17 AM

NON-CONFORMANCE Region NSW1 Wednesday, 10 January 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Wednesday, 10 January 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP5
Duration: 10/01/2024 00:15 to 10/01/2024 00:30
Amount: -20 MW
Constraint: NC-N_VP5

Auto-generated on behalf of Manager NEM Real Time Operations
113091NON-CONFORMANCE07/01/2024 01:05:14 AM

NON-CONFORMANCE Region VIC1 Sunday, 7 January 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Sunday, 7 January 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: YWPS1
Duration: 07/01/2024 00:55 to 07/01/2024 01:05
Amount: -23 MW
Constraint: NC-V_YWPS1

Auto-generated on behalf of Manager NEM Real Time Operations
113044NON-CONFORMANCE04/01/2024 04:45:12 AM

NON-CONFORMANCE Region QLD1 Thursday, 4 January 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 4 January 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BARCALDN
Duration: 04/01/2024 04:30 to 04/01/2024 04:45
Amount: 9 MW
Constraint: NC-Q_BARCALDN

Auto-generated on behalf of Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm