QNI Minor testing (NSW to Qld) 16th December 2023
Refer to market notice 110640
There is an opportunity for testing QNI Minor for flows from NSW to Qld up to 750 MW on Tuesday 16th December from 0930 to 1800hrs.
This test includes a trip and reclose of a line in northern NSW.
Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade
Ben Blake
AEMO Operations
STPASA - Update to the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/12/2023
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 112327 has been updated at 1400 hrs 15/12/2023 to the following:
From 1230 hrs to 1430 hrs 19/12/2023.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 798 MW.
From 1600 hrs to 2030 hrs 19/12/2023.
The forecast capacity reserve requirement is 1415 MW.
The minimum capacity reserve available is 1314 MW.
AEMO Operations
Network Augmentation Commissioned - SA Region - 15/12/2023
Network Augmentation Commissioned - SA Region - 15/12/2023
Commissioned:
Bundey 330kV substation, 330kV East Bus and 330kV West Bus.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 14/12/2023
Cancellation of Actual (LOR1) condition in the NSW region - 14/12/2023
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.112357 is cancelled at 1940 hrs 14/12/2023.
Manager NEM Real Time Operations
Network Augmentation Commissioned - QLD Region - 14/12/2023
Network Augmentation Commissioned - QLD Region - 14/12/2023
Commissioned:
R15 MacIntyre 330 kV Switching Station
R14 Tummaville - R15 MacIntyre No.9918 330 kV Line
R14 Tummaville - R15 MacIntyre No.9919 330 kV Line
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 14/12/2023
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 14/12/2023
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1630 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 1377 MW
The minimum capacity reserve available is 874 MW
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/12/2023
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 112299 has been updated at 1330 hrs to the following:
[1.] From 1600 hrs 14/12/2023 to 1730 hrs 14/12/2023.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.
[2.] From 1800 hrs 14/12/2023 to 2000 hrs 14/12/2023.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 744 MW.
Manager NEM Real Time Operations
STPASA - Update to the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/12/2023
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 112251 has been updated at 1400 hrs 14/12/2023 to the following:
From 1430 hrs to 1530 hrs 19/12/2023.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 854 MW.
AEMO Operations
Update - Vulnerbale lines - SA region
Vulnerable lines in SA region.
[Special Reclassification of Transmission Lines during lightning]
Refer to AEMO Electricity Market Notices 111818
At 1350 28/11/2023 hrs Tungkillo- Robertstown No.1 and No.2 275kV lines and the Robertstown No.1 and No.2 synchronous condensers were reclassified due to the elements tripping at 0534 hrs 28/11/2023
The cause of trip was identified as due to lightning.
In accordance with SO_OP_3715, AEMO now considers the following elements to be vulnerable due to lightning.
Elements: Tungkillo- Robertstown No.1 and No.2 275kV lines and the Robertstown No.1 and No.2 synchronous condensers.
Manager NEM Real Time Operations