Market Notices

117101MARKET INTERVENTION22/06/2024 05:35:16 PM

Possible intervention to manage power system security in SA Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA Region

The synchronous generating units currently expected to be synchronised in SA from 0000 hrs 24/06/2024 will be inadequate to maintain sufficient system strength in SA and hence a secure operating state.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
117100MARKET INTERVENTION22/06/2024 04:29:27 PM

Direction - SA region 22/06/2024

AEMO ELECTRICITY MARKET NOTICE.

Direction - SA region 22/06/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1635 hrs on 22/06/2024.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations
117097MARKET INTERVENTION22/06/2024 02:06:16 PM

Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE


Possible intervention to manage power system security in SA region

The synchronous generating units currently expected to be synchronised in SA from 1000 hrs 23/06/2024 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1630 hrs 22/06/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
117092NON-CONFORMANCE21/06/2024 12:05:15 PM

NON-CONFORMANCE Region QLD1 Friday, 21 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 21 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 21/06/2024 11:25 to 21/06/2024 12:05
Amount: 39 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
117083MARKET INTERVENTION20/06/2024 12:55:37 PM

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 19/06/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 19/06/2024

Refer Market Notice 117076

The AEMO Intervention Event and all associated directions are cancelled from 1300 hrs 20/06/2024

Manager NEM Real Time Operations
117076MARKET INTERVENTION19/06/2024 04:42:31 PM

Direction - SA region 19/06/2024

AEMO ELECTRICITY MARKET NOTICE.

Direction - SA region 19/06/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1650 hrs on 19/06/2024.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations
117068MARKET INTERVENTION19/06/2024 01:34:08 PM

Update - Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Possible intervention to manage power system security in SA region

Refer AEMO Electricity Market Notice 117061

The synchronous generating units currently expected to be synchronised in SA from 0100 hrs 20/06/2024 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 19/06/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
117061MARKET INTERVENTION18/06/2024 11:25:29 PM

Possible intervention to manage power system security in SA Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA Region

The synchronous generating units currently expected to be synchronised in SA from 0100 hrs 20/06/2024 will be inadequate to maintain sufficient system strength in SA and hence a secure operating state.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
117026NON-CONFORMANCE17/06/2024 05:25:12 AM

NON-CONFORMANCE Region QLD1 Monday, 17 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 17 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 17/06/2024 04:30 to 17/06/2024 05:25
Amount: -51 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
X