115012NON-CONFORMANCE23/02/2024 09:10:15 AM

NON-CONFORMANCE Region QLD1 Friday, 23 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 23 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: PUMP1
Duration: 23/02/2024 09:05 to 23/02/2024 09:10
Amount: 243 MW
Constraint: NC-Q_PUMP1

Auto-generated on behalf of Manager NEM Real Time Operations
115010RESERVE NOTICE23/02/2024 04:50:28 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 23/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 115009 is cancelled at 0445 hrs 23/02/2024.

Manager NEM Real Time Operations
115009RESERVE NOTICE23/02/2024 02:23:45 AM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 23/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1630 hrs 23/02/2024 to 1800 hrs 23/02/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1304 MW.


Manager NEM Real Time Operations
114985SETTLEMENTS RESIDUE22/02/2024 07:01:25 PM

[EventId:202402221900_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 22 February 2024 19:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1900 hrs on 22 February 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 22 February 2024.

Refer to market notice: 114980

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1900 hrs on 22 February 2024.

This is an AEMO autogenerated Market Notice.
114982SETTLEMENTS RESIDUE22/02/2024 06:30:30 PM

[EventId:202402221830_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 22 February 2024 18:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1830 hrs on 22 February 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 February 2024.

Refer to market notice: 114981

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1830 hrs on 22 February 2024.

This is an AEMO autogenerated Market Notice.
114981SETTLEMENTS RESIDUE22/02/2024 06:07:10 PM

[EventId:202402221805_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 22 February 2024 18:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1805 hrs on 22 February 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 February 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1805 hrs on 22 February 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
114980SETTLEMENTS RESIDUE22/02/2024 06:08:03 PM

[EventId:202402221800_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 22 February 2024 18:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1800 hrs on 22 February 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 22 February 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1800 hrs on 22 February 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
114968SETTLEMENTS RESIDUE22/02/2024 05:31:17 PM

[EventId:202402221730_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 22 February 2024 17:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 22 February 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 22 February 2024.

Refer to market notice: 114956

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1730 hrs on 22 February 2024.

This is an AEMO autogenerated Market Notice.
114959NON-CONFORMANCE22/02/2024 03:00:18 PM

NON-CONFORMANCE Region SA1 Thursday, 22 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Thursday, 22 February 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: HPRG1, HPRL1
Aggregate Dispatch Group: HORNSDPR_ADG1
Duration: 22/02/2024 14:55 to 22/02/2024 15:00
Amount: 12 MW
Constraint: NC-S_HORNSDPR_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations