Filter by category
Filter by Date
Non-credible contingency event - NSW region - 26/04/2024
Non-credible contingency event - NSW region - 26/04/2024
At 1112 hrs the Griffith to Darlington Point 132kV line (99K) and the Darlington Point BESS disconnected.
AEMO did not instruct load shedding.
AEMO observed 5 MW of electrical load lost.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
[EventId:202404241735_review] Prices for interval 24-Apr-2024 17:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 24 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Apr-2024 17:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202404241730_review] Prices for interval 24-Apr-2024 17:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1725 hrs on 24 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Apr-2024 17:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202404241725_review] Prices for interval 24-Apr-2024 17:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1720 hrs on 24 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Apr-2024 17:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202404241720_review] Prices for interval 24-Apr-2024 17:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1715 hrs on 24 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Apr-2024 17:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202404241715_review] Prices for interval 24-Apr-2024 17:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1710 hrs on 24 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Apr-2024 17:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202404241710_review] Prices for interval 24-Apr-2024 17:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1705 hrs on 24 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Apr-2024 17:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202404241405_review] Prices for interval 24-Apr-2024 14:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1400 hrs on 24 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Apr-2024 14:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202404241400_review] Prices for interval 24-Apr-2024 14:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1355 hrs on 24 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Apr-2024 14:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.