Filter by category
Filter by Date
Direction - SA region 15/07/2024
Direction - SA region 15/07/2024
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 15/07/2024.
Intervention pricing does not apply to this AEMO intervention event.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
Direction - SA region 15/07/2024
Direction - SA region 15/07/2024
Refer to Market Notice 117347
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1600 hrs 15/07/2024
Type of resource: generating unit
Required actions: synchronise and follow dispatch targets at 2200 hrs 15/07/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1500 hrs 16/07/2024
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Update - Foreseeable AEMO intervention in SA region
Update - Foreseeable AEMO intervention in SA region
Refer AEMO Electricity Market Notice 117346
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2200 hrs 15/07/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
AEMO estimates that, in the absence of sufficient market response by 1600 hrs 15/07/2024, AEMO may need to intervene by issuing a direction.
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2230 hrs 15/07/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
CHG0090717 | Cancelled | Production | NSW Marketnet Router Replacement
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: Market Network
Change Title: NSW Marketnet Router Replacement
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
CHG0090718 | Cancelled | Production | QLD Marketnet Router Replacement
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: Market Network
Change Title: QLD Marketnet Router Replacement
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
NON-CONFORMANCE Region QLD1 Sunday, 14 July 2024
NON-CONFORMANCE QLD1 Region Sunday, 14 July 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 14/07/2024 16:35 to 14/07/2024 16:50
Amount: -66 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Sunday, 14 July 2024
NON-CONFORMANCE VIC1 Region Sunday, 14 July 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: YWPS1
Duration: 14/07/2024 01:40 to 14/07/2024 01:45
Amount: -35 MW
Constraint: NC-V_YWPS1
Auto-generated on behalf of Manager NEM Real Time Operations
CHG0091275 | Production | MSATS - eMDM Maintenance AKS v1.28 upgrade
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: MSATS - eMDM Maintenance AKS v1.28 upgrade
Change Start Date & Time: 21/07/2024 10:00:00 AEST
Change End Date & Time: 21/07/2024 14:00:00 AEST
Outage Start Date & Time: 21/07/2024 10:00:00 AEST
Outage End Date & Time: 21/07/2024 14:00:00 AEST
Environment: Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .