Filter by category
Filter by Date
Cancellation of Actual (LOR1) condition in the Qld Region - 14/05/2024
Cancellation of Actual (LOR1) condition in the Qld region - 14/05/2024
The Actual LOR1 Condition in the Qld Region advised in AEMO Electricity Market Notice No.116615 is cancelled at 1815 hrs 14/05/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD Region on 14/05/2024
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 14/05/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs.
The forecast capacity reserve requirement is 830 MW.
The minimum capacity reserve available is 727 MW.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 09/05/2024
Cancellation of Actual (LOR1) condition in the NSW region - 09/05/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.116566 is cancelled at 1915 hrs 09/05/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/05/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/05/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs.
The capacity reserve requirement is 1450 MW
The minimum capacity reserve available is 964 MW
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 08/05/2024
Cancellation of Actual (LOR1) condition in the NSW region - 08/05/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.116547 is cancelled at 1915 hrs 08/05/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 08/05/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 08/05/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs.
The capacity reserve requirement is 1450 MW
The minimum capacity reserve available is 1417 MW
Manager NEM Real Time Operations
[EventId:202405081300_review] Prices for interval 08-May-2024 13:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1255 hrs on 8 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-May-2024 13:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405081255_review] Prices for interval 08-May-2024 12:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1250 hrs on 8 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-May-2024 12:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405081250_review] Prices for interval 08-May-2024 12:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1245 hrs on 8 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-May-2024 12:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.