PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 07/11/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120047 is cancelled at 0245 hrs 07/11/2024.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 07/11/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 1119967 has been updated at 0115 hrs to the following:
[1.] From 1730 hrs 07/11/2024 to 1800 hrs 07/11/2024.
The forecast capacity reserve requirement is 1104 MW.
The minimum capacity reserve available is 722 MW.
[2.] From 1830 hrs 07/11/2024 to 1900 hrs 07/11/2024.
The forecast capacity reserve requirement is 1116 MW.
The minimum capacity reserve available is 801 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 07/11/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120044 has been updated at 0100 hrs to the following:
[1.] From 1800 hrs 07/11/2024 to 1830 hrs 07/11/2024.
The forecast capacity reserve requirement is 702 MW.
The minimum capacity reserve available is 684 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/11/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 07/11/2024 to 1830 hrs 07/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1293 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 07/11/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1730 hrs 07/11/2024 to 1900 hrs 07/11/2024.
The forecast capacity reserve requirement is 747 MW.
The minimum capacity reserve available is 589 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Cancellation of Project Energy Connect (PEC-1) testing on 6th November 2024
Refer to market notice 119963
The Project Energy Connect (PEC-1) testing on 6th November has now been cancelled.
Terry Liu
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 08/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 119918 is cancelled at 1400 hrs 06/11/2024
No LOR condition is currently forecast in the STPASA period.
AEMO Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 07/11/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
From 1730 hrs 07/11/2024 to 1900 hrs 07/11/2024.
The forecast capacity reserve requirement is 1112 MW.
The minimum capacity reserve available is 886 MW.
Manager NEM Real Time Operations
Correction to testing time for Project Energy Connect (PEC-1) 6th November 2024 for flows in both directions
Refer to market notice 119961
This is correction to Project Energy Connect (PEC-1) testing time issued in previous notice 119961.
Testing time is on 6th November from 11:00 hrs to 22:00 hrs.
The test is for flows in both directions up to 50 MW. This test includes a trip and reclose of a line in South Australia. Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.
Mya San
AEMO Operations