NON-CONFORMANCE Region SA1 Monday, 21 October 2024
NON-CONFORMANCE SA1 Region Monday, 21 October 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BLYTHB1
Duration: 21/10/2024 10:55 to 21/10/2024 11:05
Amount: 50 MW
Constraint: NC-S_BLYTHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Monday, 21 October 2024
NON-CONFORMANCE VIC1 Region Monday, 21 October 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GLRWNSF1
Duration: 21/10/2024 09:50 to 21/10/2024 10:25
Amount: 62 MW
Constraint: NC-V_GLRWNSF1
Auto-generated on behalf of Manager NEM Real Time Operations
CHG0098496 | Completed | Production | QLD Marketnet Router Replacement
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Market Network
Change Title: QLD Marketnet Router Replacement
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0098837 | Pre-Production | EMMS-Pre-Production Bay transfer for Core switch Refresh
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System_PreProd
Change Title: EMMS-Pre-Production Bay transfer for Core switch Refresh
Change Start Date & Time: 22/10/2024 07:00:00 AEST
Change End Date & Time: 22/10/2024 19:30:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Pre-Production
Participant Impact and Requirements: A Bay transfer is scheduled for 22nd October is not expected to have any impact. If any issues are identified because of this maintenance activity, please contact the AEMO Support Hub 1300 236 600.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
Inter-regional transfer limit variation - Tamworth No 1 330 kV bus and Tamworth - Armidale No. 86 330 kV Line - NSW region - 19/10/2024
Tamworth No 1 330 kV bus and Tamworth - Armidale No. 86 330 kV Line - NSW region - 19/10/2024
A planned outage of Tamworth No 1 330 kV bus in the NSW region was scheduled from 1100 hrs 18/10/2024 to 1700 hrs 20/10/2024.
A planned outage of Tamworth - Armidale No. 86 330 kV Line in the NSW region was scheduled from 0500 hrs 09/10/2024 to 1700 hrs 20/10/2024.
The outage has been completed by 1250 hrs 19/10/2024.
Constraint set(s) invoked:
N-ARTW_86
N-LDTW_84
N-TW_SVC
N-TW_330_BUS1
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1-QLD1
T-V-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Friday, 18 October 2024
NON-CONFORMANCE VIC1 Region Friday, 18 October 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BRYB2WF2
Duration: 18/10/2024 16:50 to 18/10/2024 17:10
Amount: 10 MW
Constraint: NC-V_BRYB2WF2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Friday, 18 October 2024
NON-CONFORMANCE SA1 Region Friday, 18 October 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: HPR1
Duration: 18/10/2024 16:40 to 18/10/2024 16:55
Amount: 22 MW
Constraint: NC-S_HPR1
Auto-generated on behalf of Manager NEM Real Time Operations
CHG0099243 | Pre-Production | Maintenance activities to be performed on the Declared Wholesale Gas Market Systems Pre-Production
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Declared Wholesale Gas Market (DWGM)
Change Title: Maintenance activities to be performed on the Declared Wholesale Gas Market Systems Pre-Production.
Change Start Date & Time: 23/10/2024 07:00:23 AEST
Change End Date & Time: 23/10/2024 17:30:33 AEST
Outage Start Date & Time: 23/10/2024 08:00:00 AEST
Outage End Date & Time: 23/10/2024 12:30:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: This is a regular procedure to allow routine maintenance. short service outages over the day for DWGM services, includiing MIBB and Web Exchanger.
Pre-Production Declared Wholesale Gas Market Systems (DWGM)
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
NON-CONFORMANCE Region VIC1 Friday, 18 October 2024
NON-CONFORMANCE VIC1 Region Friday, 18 October 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BULBES1
Duration: 18/10/2024 11:05 to 18/10/2024 11:25
Amount: 20 MW
Constraint: NC-V_BULBES1