Market Notices

118406MARKET SYSTEMS23/09/2024 03:44:02 PM

CHG0098666 | Production | Telco Outage Notification - Telstra Melbourne Indial (03 9609 XXXX-XXXX)

Change Number: CHG0098666

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Cisco IP Phone

Change Title: Telco Outage Notification - Telstra Melbourne Indial (03 9609 XXXX-XXXX)

Change Start Date & Time: 08/09/2024 00:00:00 AEST

Change End Date & Time: 08/09/2024 06:00:00 AEST

Outage Start Date & Time:

Outage End Date & Time:

Environment: Production

Participant Impact and Requirements: Outage Duration:
3 x 15 Minutes

Impacts:

Reduced redundancy for Inbound and Outbound Calls (automatically rerouted via Perth).

Support Information:

Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?d=pp_services_status for any planned/unplanned maintenance activities .




     
118405MARKET SYSTEMS23/09/2024 03:36:16 PM

CHG0098660 | Production | Telco Outage Notification - Telstra Melbourne Indial (03 9609 XXXX-XXXX)

Change Number: CHG0098660

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Cisco IP Phone

Change Title: Telco Outage Notification - Telstra Melbourne Indial (03 9609 XXXX-XXXX)

Change Start Date & Time: 24/09/2024 00:00:00 AEST

Change End Date & Time: 24/09/2024 06:00:00 AEST

Outage Start Date & Time:

Outage End Date & Time:

Environment: Production

Participant Impact and Requirements: Outage Duration:
1 x 3 Hours

Impacts:
Reduced redundancy for Inbound and Outbound Calls (automatically rerouted via Perth).

Support Information:

Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?d=pp_services_status for any planned/unplanned maintenance activities .

     
118331MARKET SYSTEMS20/09/2024 10:19:05 AM

CHG0098562 | Pre-Production | Pre-Production Electricity Market Management System (EMMS) Maintenance - Outages

Change Number: CHG0098562

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Electricity Market Management System_PreProd

Change Title: Pre-Production Electricity Market Management System (EMMS) Maintenance - Outages

Change Start Date & Time: 23/09/2024 14:00:00 AEST
Change End Date & Time: 26/09/2024 17:00:00 AEST
Outage Start Date & Time: 24/09/2024 10:00:00 AEST
Outage End Date & Time: 26/09/2024 17:00:00 AEST

Environment: Pre-Production

Participant Impact and Requirements: This Maintenance activity may cause intermittent outages to below applications during the outage period .

Impacted Systems:
1.EMMS systems (Dispatch/ PASA/ Forecasting/ Settlements)
2.Identity Service will be running only for authentication purposes.
3.Web Portal including menu items (Markets, Internal & Public portal)
4.GSH
5.GBB
6.Any GAS systems that have a NEMA / WARA database connection.
7.MSATS
8.CDR
9.DERR

If any ongoing issues are identified, please contact the AEMO Support Hub 1300 236 600.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
     
118313MARKET SYSTEMS18/09/2024 12:09:04 PM

CHG0098133 | Production | NEM Reform - RMI (Retail Market Improvements) MSATS 54.0

Change Number: CHG0098133
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Market Settlement & Transfer System
Change Title: NEM Reform - RMI (Retail Market Improvements) MSATS 54.0
Change Start Date & Time: 29/09/2024 10:00:00 AEST
Change End Date & Time: 29/09/2024 17:00:00 AEST
Outage Start Date & Time: 29/09/2024 10:00:00 AEST
Outage End Date & Time: 29/09/2024 14:00:00 AEST
Environment: Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.

Meter data processing and RM reports will not be available during the outage period.

User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.

MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage

NMI Discovery will not be available during the outage period.

CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
     
118301INTER-REGIONAL TRANSFER17/09/2024 12:21:32 PM

Inter-regional transfer limit variation -South East to Tailem Bend No 1 275 KV Line - SA region - 17/09/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - South East to Tailem Bend No 1 275 KV Line - SA region - 17/09/2024

At 1034 hrs 17/09/2024 there was a short notice outage of South East to Tailem Bend No 1 275 KV Line.

The following constraint set(s) invoked at 1035 hrs 20/09/2024
S-TBSE,
S-BC_CP

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA,NSW1-QLD1,T-V-MNSP1,V-S-MNSP1,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
118299RESERVE NOTICE16/09/2024 07:16:21 PM

Cancellation of Actual (LOR1) condition in the NSW region - 16/09/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 16/09/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.118298 is cancelled at 1915 hrs 16/09/2024.

Manager NEM Real Time Operations
     
118298RESERVE NOTICE16/09/2024 06:16:31 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/09/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/09/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs

The capacity reserve requirement is 1400 MW
The minimum capacity reserve available is 1274 MW

Manager NEM Real Time Operations
     
118271INTER-REGIONAL TRANSFER14/09/2024 01:26:46 PM

Inter-regional transfer limit variation - Braemar No2 330 kV / 275 kV Transformer. - QLD region - 14/09/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Braemar No2 330 kV / 275 kV Transformer. - QLD region - 14/09/2024

At 1320 hrs 14/09/2024 there was a short notice outage of Braemar No2 330 kV / 275 kV Transformer.

The following constraint set(s) invoked at 1320 hrs 14/09/2024
Q-BRTX2

This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
118270MARKET SYSTEMS13/09/2024 04:37:32 PM

CHG0098210 | Cancelled | Production | AEMO will be undertaking maintenance activities on the NEMSETTLEMENTSR system

Change Number: CHG0098210
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: Cohesity
Change Title: AEMO will be undertaking maintenance activities on the NEMSETTLEMENTSR system.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm