[EventId:202412031145_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 03 December 2024 11:45
Issued by Australian Energy Market Operator Ltd at 1145 hrs on 3 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1145 hrs on 3 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Cancellation of Actual (LOR1) condition in the NSW region - 02/12/2024
Cancellation of Actual (LOR1) condition in the NSW region - 02/12/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.121384 is cancelled at 1920 hrs 02/12/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 02/12/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 02/12/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs
The capacity reserve requirement is 1370 MW
The minimum capacity reserve available is 1066 MW
Manager NEM Real Time Operations
INC0138848 - ALERT - EMMS - RESOLVED
The service interruption relating to the Electricity Market Management System service has been resolved.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
INC0138848 - ALERT - EMMS
SERVICE INTERRUPTION - ALERT
AEMO is experiencing a service interruption relating to the Electricity Market Management System service.
AEMO is working on the issue and will provide updates as more information becomes available.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
[EventId:202412021330_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 02 December 2024 13:30
Issued by Australian Energy Market Operator Ltd at 1330 hrs on 2 December 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 2 December 2024.
Refer to market notice: 121358
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1330 hrs on 2 December 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202412021105_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 02 December 2024 11:05
Issued by Australian Energy Market Operator Ltd at 1105 hrs on 2 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 2 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1105 hrs on 2 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Cancellation - Foreseeable intervention to manage power system security in SA region 30/11/2024
Cancellation - Foreseeable intervention to manage power system security in SA region 30/11/2024
Refer Market Notice 121281
AEMO no longer foresees a possible requirement for intervention to manage power system security in SA region. The advice of possible intervention is cancelled from 0915 hrs 30/11/2024.
Manager NEM Real Time Operations
Update - Foreseeable AEMO intervention in SA region
Update - Foreseeable AEMO intervention in SA region
Refer AEMO Electricity Market Notice 121280
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 1100 hrs 30/11/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
AEMO estimates that, in the absence of sufficient market response by 0900 hrs 30/11/2024, AEMO may need to intervene by issuing a direction.
Manager NEM Real Time Operations