Filter by category
Filter by Date
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 21/01/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 21/01/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is not forecast in Pre Dispatch
The capacity reserve requirement is 1360 MW
The minimum capacity reserve available is 1354 MW
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 21/01/2024
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 21/01/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 1238 MW
The minimum capacity reserve available is 988 MW
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the QLD region - 19/01/2024
Cancellation of Actual (LOR1) condition in the QLD region - 19/01/2024
The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.113498 is cancelled at 2000 hrs 19/01/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 19/01/2024
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 19/01/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1730 hrs.
The Actual LOR1 condition is not forecast in Pre Dispatch
The capacity reserve requirement is 982 MW
The minimum capacity reserve available is 938 MW
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the QLD region - 18/01/2024
Cancellation of Actual (LOR1) condition in the QLD region - 18/01/2024
The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.113424 is cancelled at 1815 hrs 18/01/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 18/01/2024
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 18/01/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1530 hrs.
The Actual LOR1 condition is forecast to exist until 2000 hrs
The capacity reserve requirement is 952 MW
The minimum capacity reserve available is 857 MW
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 14/12/2023
Cancellation of Actual (LOR1) condition in the NSW region - 14/12/2023
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.112357 is cancelled at 1940 hrs 14/12/2023.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 14/12/2023
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 14/12/2023
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1630 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 1377 MW
The minimum capacity reserve available is 874 MW
Manager NEM Real Time Operations
Request for Generator Recall Information for 14/12/2023 for QLD Region
Refer to AEMO Electricity Market Notice no. 112198. Additional generation in QLD could assist in alleviating the forecast LOR condition in NSW.
Please provide Generator Recall Information for the period 14/12/2023, by 1200 hrs on 13/12/2023 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.
SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf
Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf
AEMO Operations