Market Notices

120527MARKET INTERVENTION16/11/2024 02:39:52 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 120498

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1700 hrs 16/11/2024.

The direction update is issued at 1440 hrs 16/11/2024.

Manager NEM Real Time Operations
     
120526NON-CONFORMANCE16/11/2024 02:00:25 PM

NON-CONFORMANCE Region QLD1 Saturday, 16 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Saturday, 16 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 16/11/2024 13:55 to 16/11/2024 14:00
Amount: -15 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
120522NON-CONFORMANCE16/11/2024 07:35:25 AM

NON-CONFORMANCE Region NSW1 Saturday, 16 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Saturday, 16 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 16/11/2024 07:10 to 16/11/2024 07:35
Amount: -7 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
120521RECLASSIFY CONTINGENCY15/11/2024 08:44:02 PM

Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Cancellation time: 15/11/2024 20:43

Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Refer AEMO Electricity Market Notice 120519

Auto-generated on behalf of Manager NEM Real Time Operations
     
120519RECLASSIFY CONTINGENCY15/11/2024 06:43:35 PM

Reclassification of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Duration: 15/11/2024 18:43 until further notice

Constraint set(s) invoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Auto-generated on behalf of Manager NEM Real Time Operations
     
120518RECLASSIFY CONTINGENCY15/11/2024 06:39:01 PM

Cancellation of a Non-Credible Contingency Event: Collinsville - Stoney Creek 7306 132KV LINE line and Collinsville - Newlands 7121 132KV LINE line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Collinsville - Stoney Creek 7306 132KV LINE and Collinsville - Newlands 7121 132KV LINE

Cancellation time: 15/11/2024 18:38

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 120516

Auto-generated on behalf of Manager NEM Real Time Operations
     
120517RECLASSIFY CONTINGENCY15/11/2024 06:24:04 PM

Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Cancellation time: 15/11/2024 18:23

Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Refer AEMO Electricity Market Notice 120478

Auto-generated on behalf of Manager NEM Real Time Operations
     
120516RECLASSIFY CONTINGENCY15/11/2024 05:34:50 PM

Reclassification of a Non-Credible Contingency Event: Collinsville - Stoney Creek 7306 132KV LINE line and Collinsville - Newlands 7121 132KV LINE line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Collinsville - Stoney Creek 7306 132KV LINE and Collinsville - Newlands 7121 132KV LINE

Duration: 15/11/2024 17:34 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
120501NON-CONFORMANCE15/11/2024 02:40:19 PM

NON-CONFORMANCE Region QLD1 Friday, 15 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 15 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 15/11/2024 14:20 to 15/11/2024 14:40
Amount: -14 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
X