120740RESERVE NOTICE21/11/2024 10:29:03 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 25/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120711 has been updated at 0900 hrs 21/11/2024 to the following:

From 1530 hrs to 1900 hrs 25/11/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 248 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
120739RESERVE NOTICE21/11/2024 10:28:02 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120734 has been updated at 0900 hrs 21/11/2024 to the following:

1. From 1300 hrs to 1430 hrs 26/11/2024.
The forecast capacity reserve requirement is 685 MW.
The minimum capacity reserve available is 154 MW.

2. From 1830 hrs to 2100 hrs 26/11/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 38 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
120737NON-CONFORMANCE21/11/2024 02:10:16 AM

NON-CONFORMANCE Region NSW1 Thursday, 21 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 21 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP5
Duration: 21/11/2024 01:55 to 21/11/2024 02:10
Amount: -20 MW
Constraint: NC-N_VP5

Auto-generated on behalf of Manager NEM Real Time Operations
     
120734RESERVE NOTICE20/11/2024 10:18:25 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120726 has been updated at 2200 hrs 20/11/2024 to the following:

From 1330 hrs 26/11/2024 to 2000 hrs 26/11/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 130 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
120726RESERVE NOTICE20/11/2024 05:11:53 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120712 has been updated at 1600 hrs 20/11/2024 to the following:

1. From 1400 hrs to 1530 hrs 26/11/2024.
The forecast capacity reserve requirement is 699 MW.
The minimum capacity reserve available is 132 MW.

2. From 1900 hrs to 2030 hrs 26/11/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 149 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
120724GENERAL NOTICE21/11/2024 12:37:48 PM

Network Augmentation Commissioned - QLD Region - 21/11/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - QLD Region - 21/11/2024

Commissioned:

Belmont No.2 275 kV 150 MVar reactor

Manager NEM Real Time Operations
     
120723MARKET INTERVENTION20/11/2024 04:29:17 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 120680

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1500 hrs 21/11/2024.

The direction update is issued at 1630 hrs 20/11/2024.

Manager NEM Real Time Operations
     
120722MARKET INTERVENTION20/11/2024 04:28:21 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 120679

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1330 hrs 21/11/2024.

The direction update is issued at 1630 hrs 20/11/2024.

Manager NEM Real Time Operations
     
120721NON-CONFORMANCE20/11/2024 03:35:26 PM

NON-CONFORMANCE Region QLD1 Wednesday, 20 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 20 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 20/11/2024 06:35 to 20/11/2024 15:35
Amount: -45 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     