Market Notices

117828PRICES UNCHANGED27/08/2024 10:25:49 AM

[EventId:202408271015_confirmed] Prices for interval 27-Aug-2024 10:15 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1020 hrs on 27 August 2024

PRICES ARE NOW CONFIRMED for trading interval 27-Aug-2024 10:15.

In accordance with Market Notice 117823 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
117827PRICES UNCHANGED27/08/2024 10:21:47 AM

[EventId:202408271010_confirmed] Prices for interval 27-Aug-2024 10:10 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1020 hrs on 27 August 2024

PRICES ARE NOW CONFIRMED for trading interval 27-Aug-2024 10:10.

In accordance with Market Notice 117822 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
117826PRICES UNCHANGED27/08/2024 10:20:28 AM

[EventId:202408271005_confirmed] Prices for interval 27-Aug-2024 10:05 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1020 hrs on 27 August 2024

PRICES ARE NOW CONFIRMED for trading interval 27-Aug-2024 10:05.

In accordance with Market Notice 117821 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
117825PRICES UNCHANGED27/08/2024 10:27:02 AM

[EventId:202408270955_confirmed] Prices for interval 27-Aug-2024 09:55 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1020 hrs on 27 August 2024

PRICES ARE NOW CONFIRMED for trading interval 27-Aug-2024 09:55.

In accordance with Market Notice 117819 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
117737GENERAL NOTICE21/08/2024 10:37:27 AM

Planned outage of Kerang - Wemen 220 kV line in the VIC region on 23/08/2024.

AEMO ELECTRICITY MARKET NOTICE

The Kerang - Wemen 220 kV line in the Victorian (VIC) region is planned to be out of service from 0600 hrs to 1800 hrs on 23/08/2024.

A credible contingency event during this planned outage may require:
- Load shedding in the Victorian outer grid; and/ or
- Market intervention, such as the issuing of directions.

Refer AEMO Network Outage Schedule (NOS) for further details.

AEMO Operations
117694GENERAL NOTICE16/08/2024 10:44:53 AM

Network Augmentation Commissioned - NSW Region - 16/08/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - NSW Region - 16/08/2024

Commissioned: Munmorah - Waratah S BESS 2Y 330 kV Line

Manager NEM Real Time Operations
117691GENERAL NOTICE15/08/2024 10:28:59 PM

Network Augmentation Commissioned - NSW Region - 15/08/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - NSW Region - 15/08/2024

Commissioned: Munmorah - Waratah S BESS 2W 330 kV Line

Manager NEM Real Time Operations
117670GENERAL NOTICE14/08/2024 09:15:50 AM

Planned outage of Nebo to Broadsound no. 8846 275 kV line in the QLD region beginning on 16/08/2024

AEMO ELECTRICITY MARKET NOTICE

The Nebo to Broadsound no. 8846 275 kV line in the Queensland (QLD) region is planned to be out of service from 0600 hrs 16/08/2024 to 1700 hrs 18/08/2024.

This outage is considered a High Impact Outage (HIO) as the outage recall is greater than 30 minutes.
A credible contingency event during this planned outage may require market intervention, such as the issuing of directions.

Refer AEMO Network Outage Schedule (NOS) for further details.

AEMO Operations
117650GENERAL NOTICE12/08/2024 09:31:53 AM

QNI Minor testing (NSW to Qld) 12th August 2024

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 116052

There is an opportunity for testing QNI Minor for flows from NSW to Qld up to 850 MW on Monday 12th August 2024 from 1100 to 1700hrs.

This test includes a trip and reclose of a line in northern NSW.

Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade

Ben Blake
AEMO Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm