119921MARKET INTERVENTION05/11/2024 03:29:58 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 119875

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1700 hrs 06/11/2024.

The direction update is issued at 1530 hrs 05/11/2024.

Manager NEM Real Time Operations
     
119920MINIMUM SYSTEM LOAD05/11/2024 03:28:43 PM

Forecast Minimum System Load MSL1 condition in the VIC region on 10/11/2024

AEMO ELECTRICITY MARKET NOTICE

Update to Market Notice 119867 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 10/11/2024.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1760 MW
o MSL2 - 1260 MW
o MSL3 - 760 MW

The regional demand is forecast to be below the MSL1 threshold for the following period:

From 1000 hrs to 1430 hrs 10/11/2024. Minimum regional demand is forecast to be 1349 MW at 1300 hrs.

Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .

AEMO Operations
     
119919RESERVE NOTICE05/11/2024 03:27:37 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 119868 has been updated at 1400 hrs 05/11/2024 to the following:

From 1700 hrs to 1930 hrs 07/11/2024.
The forecast capacity reserve requirement is 1002 MW.
The minimum capacity reserve available is 906 MW.

AEMO Operations
     
119918RESERVE NOTICE05/11/2024 03:26:32 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 08/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 119871 has been updated at 1400 hrs 05/11/2024 to the following:

From 1730 hrs to 1800 hrs 08/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1369 MW.

AEMO Operations
     
119917RESERVE NOTICE05/11/2024 03:25:10 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 119870 has been updated at 1400 hrs 05/11/2024 to the following:

1. From 1100 hrs to 1130 hrs 07/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1366 MW.

2. From 1200 hrs to 1230 hrs 07/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1183 MW.

3. From 1800 hrs to 1830 hrs 07/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1123 MW.

AEMO Operations
     
119916RECLASSIFY CONTINGENCY05/11/2024 02:22:11 PM

Reclassification of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Duration: 05/11/2024 14:22 until further notice

Constraint set(s) invoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Auto-generated on behalf of Manager NEM Real Time Operations
     
119915SETTLEMENTS RESIDUE05/11/2024 02:00:26 PM

[EventId:202411051400_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 05 November 2024 14:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1400 hrs on 5 November 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 5 November 2024.

Refer to market notice: 119914

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1400 hrs on 5 November 2024.

This is an AEMO autogenerated Market Notice.
     
119914SETTLEMENTS RESIDUE05/11/2024 01:05:26 PM

[EventId:202411051305_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 05 November 2024 13:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1305 hrs on 5 November 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 5 November 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1305 hrs on 5 November 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
119913RESERVE NOTICE05/11/2024 01:14:49 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 06/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:

[1.] From 1800 hrs 06/11/2024 to 1830 hrs 06/11/2024.
The forecast capacity reserve requirement is 1108 MW.
The minimum capacity reserve available is 949 MW.

Manager NEM Real Time Operations
     