Filter by category
Filter by Date
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 26/01/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
[1.] From 1830 hrs 26/01/2024 to 1930 hrs 26/01/2024.
The forecast capacity reserve requirement is 1050 MW.
The minimum capacity reserve available is 1009 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 26/01/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 113762 is cancelled at 0940 hrs 26/01/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 26/01/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
[1.] From 1830 hrs 26/01/2024 to 1930 hrs 26/01/2024.
The forecast capacity reserve requirement is 1050 MW.
The minimum capacity reserve available is 1015 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 26/01/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 113743 is cancelled at 0500 hrs 26/01/2024.
Manager NEM Real Time Operations
CHG0082787 | Pre-Production | Pre-Production MSATS r50.0.5 Patch Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Pre-Production MSATS r50.0.5 Patch Release
Change Start Date & Time: 30/01/2024 12:00:00 AEST
Change End Date & Time: 30/01/2024 17:00:00 AEST
Outage Start Date & Time: 30/01/2024 12:00:00 AEST
Outage End Date & Time: 30/01/2024 14:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities.
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 28/01/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1730 hrs 28/01/2024 to 1930 hrs 28/01/2024.
The forecast capacity reserve requirement is 1190 MW.
The minimum capacity reserve available is 1165 MW.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 27/01/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No.113701 has been updated at 1400 hrs 25/01/2024 to the following:
[1.] From 1630 hrs 27/01/2024 to 1700 hrs 27/01/2024.
The forecast capacity reserve requirement is 1218 MW.
The minimum capacity reserve available is 1004 MW.
[2.] From 2030 hrs 27/01/2024 to 2130 hrs 27/01/2024.
The forecast capacity reserve requirement is 1183 MW.
The minimum capacity reserve available is 843 MW.
[3.] From 2200 hrs 27/01/2024 to 2230 hrs 27/01/2024.
The forecast capacity reserve requirement is 1133 MW.
The minimum capacity reserve available is 905 MW.
AEMO Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 26/01/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 113737 has been updated at 1445 hrs to the following:
[1.] From 1830 hrs 26/01/2024 to 1930 hrs 26/01/2024.
The forecast capacity reserve requirement is 1023 MW.
The minimum capacity reserve available is 987 MW.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 26/01/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 113720 is cancelled at 1400 hrs 25/01/2024.
AEMO Operations