[EventId:202404081300_review] Prices for interval 08-Apr-2024 13:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1255 hrs on 8 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Apr-2024 13:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202404081255_review] Prices for interval 08-Apr-2024 12:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1250 hrs on 8 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Apr-2024 12:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202404081250_review] Prices for interval 08-Apr-2024 12:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1245 hrs on 8 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Apr-2024 12:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202404081245_review] Prices for interval 08-Apr-2024 12:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1240 hrs on 8 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Apr-2024 12:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202404081240_review] Prices for interval 08-Apr-2024 12:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1235 hrs on 8 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Apr-2024 12:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Update - Network Augmentation Commissioned - QLD Region - 09/04/2024
Update - Network Augmentation Commissioned - QLD Region - 09/04/2024
Refer Market notice: 115957
Guybal Munjan 275 kV Switching Station has been cut into the existing Ross - Chalumbin No.858 275 kV line to form the following circuits:
H93 Guybal Munjan - H32 Chalumbin No.858 275 kV line
H13 Ross - H93 Guybal Munjan No.8916 275 kV line
Manager NEM Real Time Operations
Network Augmentation Commissioned - QLD Region - 04/04/2024
Network Augmentation Commissioned - QLD Region - 04/04/2024
Commissioned:
H93 Guybal Munjan 275 kV Switching Station
H13 Ross - H93 Guybal Munjan No.8916 275 kV line
Manager NEM Real Time Operations
Cancellation - Severe Space Weather Watch Notification 25/03/2024
Cancellation - Severe Space Weather Watch Notification 25/03/2024
Refer to MN 115774
The Australian Bureau of Meteorology's Space Weather forecasting centre has cancelled the following notification.
Severe space weather watch: A recent Coronal Mass Ejection associated with a solar flare is anticipated to impact the Earth within the next 48 hours.
Manager NEM Real Time Operations
Severe Space Weather Watch Notification 25/03/2024
Severe Space Weather Watch Notification 25/03/2024
The Australian Bureau of Meteorology's Space Weather Forecasting Centre has issued the following notification.
Severe space weather watch: A recent space weather event is anticipated to impact the Earth within the next 48 hours.
The effects are expected to be significant.
Increased awareness of critical infrastructure is advised.
Please monitor the SWS website for further updates at https://www.sws.bom.gov.au
If required; actions will be taken as per AEMO's system operating procedure SO_OP3715 Power System Security Guidelines.
Manager NEM Real Time Operations