STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/02/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 115063 is cancelled at 0230 hrs 24/02/2024
No LOR2 condition is currently forecast in the STPASA period.
Manager NEM RTO
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/02/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
[1.] From 1630 hrs 29/02/2024 to 1800 hrs 29/02/2024.
The forecast capacity reserve requirement is 750 MW.
The minimum capacity reserve available is 650 MW.
[2.] From 1830 hrs 29/02/2024 to 1900 hrs 29/02/2024.
The forecast capacity reserve requirement is 1050 MW.
The minimum capacity reserve available is 1050 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 23/02/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 115025 is cancelled at 1845 hrs 23/02/2024.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Friday, 23 February 2024
NON-CONFORMANCE NSW1 Region Friday, 23 February 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BW01
Duration: 23/02/2024 16:35 to 23/02/2024 17:35
Amount: 43 MW
Constraint: NC-N_BW01
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 29/02/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1530 hrs to 2130 hrs 29/02/2024.
The forecast capacity reserve requirement is 1698 MW.
The minimum capacity reserve available is 968 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 29/02/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1730 hrs to 1830 hrs 29/02/2024.
The forecast capacity reserve requirement is 1256 MW.
The minimum capacity reserve available is 1004 MW.
AEMO Operations
CHG0082690 | Production | MSATS NEM Reform Metering Exemptions and B2M r44 Schema Go-Live
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: MSATS NEM Reform Metering Exemptions and B2M r44 Schema Go-Live
Change Start Date & Time: 03/03/2024 09:00:00 AEST
Change End Date & Time: 03/03/2024 17:00:00 AEST
Outage Start Date & Time: 03/03/2024 10:00:00 AEST
Outage End Date & Time: 03/03/2024 14:00:00 AEST
Environment: Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 23/02/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 115016 has been updated at 1315 hrs to the following:
[1.] From 1730 hrs 23/02/2024 to 1900 hrs 23/02/2024.
The forecast capacity reserve requirement is 1256 MW.
The minimum capacity reserve available is 1097 MW.
Manager NEM Real Time Operations
CHG0085747 | Pre-Production | Retail Pre-Production Data refresh (CATS and EMDM)
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Retail Pre-Production Data refresh (CATS and EMDM)
Change Start Date & Time: 04/03/2024 08:00:00 AEST
Change End Date & Time: 08/03/2024 19:00:00 AEST
Outage Start Date & Time: 04/03/2024 08:00:00 AEST
Outage End Date & Time: 08/03/2024 19:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: PPD MSATS unavailble betweeb 4th March until cob 8th March 2024
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .