Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 22/01/2024
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 22/01/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1830 hrs.
The Actual LOR1 condition is forecast in Predispatch
The capacity reserve requirement is 986 MW
The minimum capacity reserve available is 969 MW
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction QLD region 22/01/2024
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction QLD region 22/01/2024
Refer Market Notice 113610
The AEMO Intervention Event and all associated directions are cancelled from 1915 hrs 22/01/2024
Manager NEM Real Time Operations
Direction - QLD region 22/01/2024
Direction - QLD region 22/01/2024
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the QLD region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).
The direction was necessary to maintain the power system in a reliable operating state.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1435 hrs on 22/01/2024.
Intervention pricing does not apply to this AEMO intervention event.
Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Monday, 22 January 2024
NON-CONFORMANCE VIC1 Region Monday, 22 January 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: YWPS4
Duration: 22/01/2024 04:15 to 22/01/2024 05:10
Amount: 27 MW
Constraint: NC-V_YWPS4
Auto-generated on behalf of Manager NEM Real Time Operations
Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 21/01/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 21/01/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 2000 hrs
The capacity reserve requirement is 1340 MW
The minimum capacity reserve available is 1103 MW
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the QLD region - 21/01/2024
Cancellation of Actual (LOR1) condition in the QLD region - 21/01/2024
The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.113570 is cancelled at 2015 hrs 21/01/2024.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 21/01/2024
Cancellation of Actual (LOR1) condition in the NSW region - 21/01/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.113576 is cancelled at 1945 hrs 21/01/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 21/01/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 21/01/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is not forecast in Pre Dispatch
The capacity reserve requirement is 1360 MW
The minimum capacity reserve available is 1354 MW
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 21/01/2024
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 21/01/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 1238 MW
The minimum capacity reserve available is 988 MW
Manager NEM Real Time Operations