Market Notices

112196MARKET SYSTEMS12/12/2023 07:05:08 AM

CHG0082097 | Production | P3062 Manifestly Incorrect Inputs (MII)? Production Release

Change Number: CHG0082097
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMMS - Dispatch
Change Title: P3062 Manifestly Incorrect Inputs (MII) Production Release
Change Start Date & Time: 12/12/2023 08:00:00 AEST
Change End Date & Time: 13/12/2023 17:30:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: Under this change , AEMO will install an updated version of a key Dispatch application (NEMDE Solutionloader) used in Production for Dispatch, 5-Minute Pre-dispatch, Pre-dispatch, and 7-Day Pre-dispatch.

Changes include:
o Extension of Automated MII Procedures to include detection of FCAS MIIs using an FCAS requirement threshold.

No outages or delays expected. AEMO will advise once complete.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
112187POWER SYSTEM EVENTS11/12/2023 04:04:48 PM

Update - Non-credible contingency event - SA region - 11/12/2023

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - SA region - 11/12/2023

Refer AEMO Electricity Market Notice 112181

At 1554 hrs the remaining Mintaro - Waterloo 132 kV Line was returned to service.

The following constraint set(s) revoked:
S-X-MNWT+CB

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
112186MARKET SYSTEMS11/12/2023 03:54:11 PM

CHG0082301 | Production | Planned System Maintenance - Electricity MMS Production Bay transfer

Change Number: CHG0082301
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System
Change Title: Planned System Maintenance - Electricity MMS Production Bay transfer
Change Start Date & Time: 11/12/2023 13:00:00 AEST
Change End Date & Time: 13/12/2023 16:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: The maintenance activity is not expected to have any impact. If any issues are identified because of this maintenance activity, please contact the AEMO Support Hub 1300 236 600 .
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
112183RESERVE NOTICE11/12/2023 03:13:48 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/12/2023

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 112160 has been updated at 1400 hrs 11/12/2023 to the following:

From 1530 hrs to 2000 hrs 14/12/2023.
The forecast capacity reserve requirement is 1385 MW.
The minimum capacity reserve available is 700 MW.


AEMO Operations
112182RESERVE NOTICE11/12/2023 03:12:58 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 14/12/2023

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 1700 hrs to 2030 hrs 14/12/2023.
The forecast capacity reserve requirement is 1287 MW.
The minimum capacity reserve available is 1019 MW.


AEMO Operations
112168MARKET SYSTEMS11/12/2023 06:40:17 AM

CHG0081726 | Completed | Production | Renewal of webMethods ESB server certificate

Change Number: CHG0081726
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Business to Business data exchange
Change Title: Renewal of webMethods ESB server certificate
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
112167MARKET SYSTEMS11/12/2023 06:39:14 AM

CHG0082105 | Completed | Production | BAU Retail Maintenance Release

Change Number: CHG0082105
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MDM - Meter Data Management
Change Title: BAU Retail Maintenance Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
112165POWER SYSTEM EVENTS11/12/2023 06:36:10 AM

Non-credible contingency event - SA region - 11/12/2023

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - SA region - 11/12/2023

At 0444 hrs the Mintaro - Waterloo 132 kV Line tripped and the Clare North - Mintaro 132 kV Line tripped at the Mintaro end only.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
112160RESERVE NOTICE10/12/2023 03:43:03 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/12/2023.

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 112042 has been updated at 1530 hrs 10/12/2023 to the following:

From 1600 hrs 14/12/2023 to 1830 hrs 14/12/2023.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1076 MW.


Manager NEM Real Time Operations