Filter by category
Filter by Date
Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS
Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer to Market Notice 120609
Direction is cancelled from: 1830 hrs 18/11/2024
Manager NEM Real Time Operations
[EventId:202411181600_confirmed] Prices for interval 18-Nov-2024 16:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1625 hrs on 18 November 2024
PRICES ARE NOW CONFIRMED for trading interval 18-Nov-2024 16:00.
In accordance with Market Notice 120617 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202411181625_confirmed] Prices for interval 18-Nov-2024 16:25 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1625 hrs on 18 November 2024
PRICES ARE NOW CONFIRMED for trading interval 18-Nov-2024 16:25.
In accordance with Market Notice 120624 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202411181620_confirmed] Prices for interval 18-Nov-2024 16:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1625 hrs on 18 November 2024
PRICES ARE NOW CONFIRMED for trading interval 18-Nov-2024 16:20.
In accordance with Market Notice 120623 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202411181615_confirmed] Prices for interval 18-Nov-2024 16:15 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1625 hrs on 18 November 2024
PRICES ARE NOW CONFIRMED for trading interval 18-Nov-2024 16:15.
In accordance with Market Notice 120622 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202411181610_confirmed] Prices for interval 18-Nov-2024 16:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1625 hrs on 18 November 2024
PRICES ARE NOW CONFIRMED for trading interval 18-Nov-2024 16:10.
In accordance with Market Notice 120621 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202411181605_confirmed] Prices for interval 18-Nov-2024 16:05 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1625 hrs on 18 November 2024
PRICES ARE NOW CONFIRMED for trading interval 18-Nov-2024 16:05.
In accordance with Market Notice 120619 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 120553
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 20/11/2024.
The direction update is issued at 1630 hrs 18/11/2024.
Manager NEM Real Time Operations
Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 120499
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1630 hrs 18/11/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0800 hrs 19/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 20/11/2024 / further notice.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations