Filter by category
Filter by Date
Cancellation - Inter-regional transfer limit variation - to manage Power System Security in NSW region - 28/11/2024
Refer AEMO Electricity Market Notice 121142
Constraint set I-QN_1000 was invoked from 0955 hrs until 1230 hrs 28/11/2024.
This constraint set contains equations with the following interconnector on the LHS;
NSW1-QLD1
Manager NEM Real Time Operations
Inter-regional transfer limit variation - to manage Power System Security in NSW region - 28/11/2024
In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked the following constraint set I-QN_1000 from 0955 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
NSW1-QLD1
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Murraylink
Inter-Regional Transfer limit variation - Murraylink
There has been an unplanned outage of Murraylink.
The following constraint set was invoked at 1405 hrs 25/11/2024
I-ML_ZERO
The constraint set contains the following interconnector on the left hand side.
V-S-MNSP1
Refer to AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Directlink - NSW region - 22/11/2024
Inter-regional transfer limit variation - Directlink - NSW region - 22/11/2024
At 1911 hrs 22/11/2024 there was an unplanned outage of the No.2 leg of Directlink.
The following constraint set(s) invoked at 1920 hrs 22/11/2024
N-X_MBTE_2
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Directlink - NSW Region
Inter-Regional Transfer limit variation - Directlink - NSW Region
There has been an unplanned outage of the No 2 Leg of Directlink .
The following constraint set was invoked at 1720 hrs 22/11/2024
N-X_MBTE_2
The constraint set contains the following interconnector on the left hand side.
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Moorabool - Sydenham No. 2 500 kV Line - VIC region - 19/11/2024
Inter-regional transfer limit variation - Moorabool - Sydenham No. 2 500 kV Line - VIC region - 19/11/2024
A planned outage of Moorabool - Sydenham No. 2 500 kV Line in the VIC region was scheduled from 1130 hrs 13/11/2024 to 1900 hrs 20/11/2024.
The outage has been completed and Moorabool - Sydenham No. 2 500 kV Line returned to service at 1640 hrs 19/11/2024
Constraint set(s) revoked: V-MLSY_NOEMTT_R
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Southpine - Rocklea 809 275 kV Line - QLD region - 18/11/2024
Inter-regional transfer limit variation - Southpine - Rocklea 809 275 kV Line - QLD region - 18/11/2024
At 1545 hrs 18/11/2024 there was an unplanned outage of Southpine - Rocklea 809 275 kV Line.
The following constraint set(s) invoked at 1545 hrs 18/11/2024
Q-RLSP_809
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Armidale to Dumaresq (8C) 330 kV line - NSW region - 17/11/2024
Inter-regional transfer limit variation - Armidale to Dumaresq (8C) 330 kV line - NSW region - 17/11/2024
A planned outage of Armidale to Dumaresq (8C) 330 kV line in the NSW region was scheduled from 0500 hrs 17/11/2024 to 1700 hrs 17/11/2024.
The outage has been completed returned to service at 1330 hrs 17/11/2024
Constraint set(s) revoked:
N-ARDM_8C
N-DM_SVC
N-TW_SVC
N-X_8C+DM+TW_SVC
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Bungama - Davenport 275 kV line - SA region - 11/11/2024
Inter-regional transfer limit variation - Bungama - Davenport 275 kV line - SA region - 11/11/2024
At 1307 hrs 11/11/2024 there was an unplanned outage of the Bungama - Davenport 275 kV line.
The following constraint set invoked at 1315 hrs 11/11/2024
S-BGDV
This constraint sets contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations