NON-CONFORMANCE Region QLD1 Wednesday, 11 December 2024
NON-CONFORMANCE QLD1 Region Wednesday, 11 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 11/12/2024 02:00 to 11/12/2024 02:20
Amount: -10 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Tuesday, 10 December 2024
NON-CONFORMANCE QLD1 Region Tuesday, 10 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 10/12/2024 17:55 to 10/12/2024 18:25
Amount: -18 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
Update - Inter-regional transfer limit variation - constraint automation to manage Power System Security in QLD region - 10 Dec 2024
Refer to MN 121688
In order to maintain the power system in a secure operating state in the QLD region, AEMO has invoked automated constraint set CA_SYD_566A36E5 from 1245 hrs to 1510 hrs.
This constraint set contains equations with the following interconnector on the LHS;
NSW1-QLD1, N-Q_MNSP1
Refer to AEMO Network Outage Scheduler (NOS) for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - constraint automation to manage Power System Security in QLD region - 10 Dec 2024
In order to maintain the power system in a secure operating state in the QLD region, AEMO has invoked automated constraint set CA_SYD_566A36E5 from 1245 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
NSW1-QLD1, N-Q_MNSP1
Refer to AEMO Network Outage Scheduler (NOS) for further information.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Tuesday, 10 December 2024
NON-CONFORMANCE QLD1 Region Tuesday, 10 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 10/12/2024 00:55 to 10/12/2024 01:00
Amount: -13 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202412091800_review] Prices for interval 09-Dec-2024 18:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1755 hrs on 9 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 09-Dec-2024 18:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412091755_review] Prices for interval 09-Dec-2024 17:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1750 hrs on 9 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 09-Dec-2024 17:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412091750_review] Prices for interval 09-Dec-2024 17:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1745 hrs on 9 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 09-Dec-2024 17:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412091745_review] Prices for interval 09-Dec-2024 17:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1740 hrs on 9 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 09-Dec-2024 17:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.