Filter by category
Filter by Date
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121171 is cancelled at 1615 hrs 28/11/2024.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121151 has been updated at 1415 hrs to the following:
[1.] From 0800 hrs 29/11/2024 to 0930 hrs 29/11/2024.
The forecast capacity reserve requirement is 941 MW.
The minimum capacity reserve available is 860 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
[EventId:202411271510_confirmed] Prices for interval 27-Nov-2024 15:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1418 hrs on 28 November 2024
PRICES ARE NOW CONFIRMED for trading interval 27-Nov-2024 15:10.
In accordance with Market Notice 121092 AEMO has reviewed this trading interval and determined that:
- Over-Constrained Dispatch has been resolved for this interval
Changed Prices ($/MWh)
TYPE
Region Original Adjusted
Price Price
ENERGY
VIC1 -$30.00 -$29.50
RAISE60SEC
NSW1 $0.10 $0.05
QLD1 $0.10 $0.05
SA1 $0.10 $0.05
VIC1 $0.10 $0.05
This is an AEMO autogenerated Market Notice.
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/11/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Periods:
[1.] From 0800 hrs 29/11/2024 to 1000 hrs 29/11/2024.
The forecast capacity reserve requirement is 968 MW.
The minimum capacity reserve available is 816 MW.
[2.] From 1330 hrs 29/11/2024 to 1500 hrs 29/11/2024.
The forecast capacity reserve requirement is 1156 MW.
The minimum capacity reserve available is 1102 MW.
[3.] From 1530 hrs 29/11/2024 to 1700 hrs 29/11/2024.
The forecast capacity reserve requirement is 1131 MW.
The minimum capacity reserve available is 1075 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Update to the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121139 has been updated at 1100 hrs 28/11/2024 to the following:
1. From 0800 hrs to 0930 hrs 29/11/2024.
The forecast capacity reserve requirement is 1023 MW.
The minimum capacity reserve available is 1011 MW.
2. From 1100 hrs to 1500 hrs 29/11/2024.
The forecast capacity reserve requirement is 1281 MW.
The minimum capacity reserve available is 1094 MW.
3. From 1530 hrs to 1700 hrs 29/11/2024.
The forecast capacity reserve requirement is 1189 MW.
The minimum capacity reserve available is 1047 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update to the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121024 has been updated at 1000 hrs 28/11/2024 to the following:
1. From 1100 hrs to 1500 hrs 29/11/2024.
The forecast capacity reserve requirement is 1332 MW.
The minimum capacity reserve available is 1171 MW.
2. From 1530 hrs to 1700 hrs 29/11/2024.
The forecast capacity reserve requirement is 1205 MW.
The minimum capacity reserve available is 1126 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
Planned outage of the Red Cliffs - Wemen - Kerang 220kV line in the VIC region on 30/11/2024.
The Red Cliffs - Wemen - Kerang 220kV line in the Victorian (VIC) region is planned to be out of service from 0400 hrs to 1430 hrs on 30/11/2024.
A credible contingency event during this planned outage may require:
- Load shedding in the Victorian outer grid; and/ or
- Market intervention, such as the issuing of directions.
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO Operations
Cancellation of Actual (LOR2) condition in the NSW region - 27/11/2024
Cancellation of Actual (LOR2) condition in the NSW region - 27/11/2024
The Actual LOR2 Condition in the NSW Region advised in AEMO Electricity Market Notice No.121101 is cancelled at 1645 hrs 27/11/2024.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 28/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121066 is cancelled at 1530 hrs 27/11/2024.
Manager NEM Real Time Operations