121794RESERVE NOTICE12/12/2024 03:52:58 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 17/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 1800 hrs to 1900 hrs 17/12/2024.
The forecast capacity reserve requirement is 990 MW.
The minimum capacity reserve available is 836 MW.

AEMO Operations
     
121793RESERVE NOTICE12/12/2024 03:51:43 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 15/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1700 hrs to 1830 hrs 15/12/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1062 MW.

AEMO Operations
     
121792RESERVE NOTICE12/12/2024 03:47:24 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 17/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

1. From 1200 hrs to 1430 hrs 17/12/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.

2. From 2000 hrs to 2200 hrs 17/12/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 710 MW.

AEMO Operations
     
121791RESERVE NOTICE12/12/2024 03:45:39 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121719 has been updated at 1400 hrs 12/12/2024 to the following:

1. From 1230 hrs to 1430 hrs 16/12/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 825 MW.

2. From 2030 hrs to 2200 hrs 16/12/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.

AEMO Operations
     
121782RESERVE NOTICE12/12/2024 01:09:03 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 12/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

[1.] From 1630 hrs 13/12/2024 to 1830 hrs 13/12/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 881 MW.

[2.] From 1900 hrs 13/12/2024 to 1930 hrs 13/12/2024.
The forecast capacity reserve requirement is 1459 MW.
The minimum capacity reserve available is 1362 MW.


Manager NEM Real Time Operations
     
121771GENERAL NOTICE12/12/2024 10:30:51 AM

NEM Local Temperature Alerts for NSW, SA, VIC from 12 Dec 2024 to 16 Dec 2024

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

NSW
Yass (39+ Deg C): 16th Dec

SA
Adelaide West Terrace (39+ Deg C): 15th Dec
Clare High School (39+ Deg C): 15th Dec
Port Augusta Ap (39+ Deg C): 14th Dec, 15th Dec

VIC
Latrobe Valley Ap (39+ Deg C): 16th Dec
Melbourne Olympic Park (39+ Deg C): 16th Dec
Mildura Ap (39+ Deg C): 15th Dec, 16th Dec
Mortlake (39+ Deg C): 16th Dec

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
     
121761RESERVE NOTICE12/12/2024 08:51:13 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 12/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

[1.] From 1730 hrs 12/12/2024 to 1930 hrs 12/12/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1075 MW.


Manager NEM Real Time Operations
     
121756RESERVE NOTICE12/12/2024 07:50:25 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 12/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

[1.] From 1730 hrs 12/12/2024 to 1900 hrs 12/12/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1283 MW.


Manager NEM Real Time Operations
     
121752RESERVE NOTICE12/12/2024 04:25:47 AM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 12/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

[1.] From 1830 hrs 12/12/2024 to 1900 hrs 12/12/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1401 MW.


Manager NEM Real Time Operations
     