PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region beginning on 10/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121702 is cancelled at 1840 hrs 10/12/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 10/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1830 hrs 10/12/2024 to 1900 hrs 10/12/2024.
The forecast capacity reserve requirement is 1320 MW.
The minimum capacity reserve available is 1197 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region beginning on 10/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121698 is cancelled at 1745 hrs 10/12/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 10/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1830 hrs 10/12/2024 to 1900 hrs 10/12/2024.
The forecast capacity reserve requirement is 1385 MW.
The minimum capacity reserve available is 1336 MW.
Manager NEM Real Time Operations
Update - Inter-regional transfer limit variation - constraint automation to manage Power System Security in QLD region - 10 Dec 2024
Refer to MN 121688
In order to maintain the power system in a secure operating state in the QLD region, AEMO has invoked automated constraint set CA_SYD_566A36E5 from 1245 hrs to 1510 hrs.
This constraint set contains equations with the following interconnector on the LHS;
NSW1-QLD1, N-Q_MNSP1
Refer to AEMO Network Outage Scheduler (NOS) for further information.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 17/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
1. From 1700 hrs to 1830 hrs 17/12/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1310 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
1. From 1500 hrs 16/12/2024 to 1630 hrs 16/12/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.
2. From 1930 hrs to 2030 hrs 16/12/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 962 MW.
AEMO Operations
Inter-regional transfer limit variation - constraint automation to manage Power System Security in QLD region - 10 Dec 2024
In order to maintain the power system in a secure operating state in the QLD region, AEMO has invoked automated constraint set CA_SYD_566A36E5 from 1245 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
NSW1-QLD1, N-Q_MNSP1
Refer to AEMO Network Outage Scheduler (NOS) for further information.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1830 hrs 08/12/2024 to 1930 hrs 08/12/2024.
The forecast capacity reserve requirement is 990 MW.
The minimum capacity reserve available is 920 MW.
Manager NEM Real Time Operations