121766MARKET INTERVENTION12/12/2024 09:31:31 AM

Cancellation - AEMO Intervention Event - SA region 11/12/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 06/12/2024

Refer to Market Notice 121721

The AEMO Intervention Event and all associated directions are cancelled from 0930 hrs on 12/12/2024.


Manager NEM Real Time Operations
     
121763MARKET INTERVENTION12/12/2024 09:30:08 AM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer to Market Notice 121722

Direction is cancelled from: 0930 hrs 12/12/2024

Manager NEM Real Time Operations
     
121745PRICES SUBJECT TO REVIEW12/12/2024 02:00:17 AM

[EventId:202412120205_review] Prices for interval 12-Dec-2024 02:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0200 hrs on 12 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 12-Dec-2024 02:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121744PRICES SUBJECT TO REVIEW12/12/2024 01:55:24 AM

[EventId:202412120200_review] Prices for interval 12-Dec-2024 02:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0155 hrs on 12 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 12-Dec-2024 02:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121743PRICES SUBJECT TO REVIEW12/12/2024 01:50:16 AM

[EventId:202412120155_review] Prices for interval 12-Dec-2024 01:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0150 hrs on 12 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 12-Dec-2024 01:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121742PRICES SUBJECT TO REVIEW12/12/2024 01:45:20 AM

[EventId:202412120150_review] Prices for interval 12-Dec-2024 01:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0145 hrs on 12 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 12-Dec-2024 01:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121741PRICES SUBJECT TO REVIEW12/12/2024 01:40:21 AM

[EventId:202412120145_review] Prices for interval 12-Dec-2024 01:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0140 hrs on 12 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 12-Dec-2024 01:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121740PRICES SUBJECT TO REVIEW12/12/2024 01:35:21 AM

[EventId:202412120140_review] Prices for interval 12-Dec-2024 01:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0135 hrs on 12 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 12-Dec-2024 01:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121739INTER-REGIONAL TRANSFER12/12/2024 01:37:40 AM

Inter-Regional Transfer limit variation - Basslink

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Basslink

There has been an unplanned outage of the Basslink interconnector.

The following constraint set was invoked at 0130 hrs 12/12/2024

I-BL_ZERO

The constraint set contains the following interconnector on the left hand side.

T-V-MNSP1

Manager NEM Real Time Operations
     