120645PRICES SUBJECT TO REVIEW18/11/2024 09:25:14 PM

[EventId:202411182130_review] Prices for interval 18-Nov-2024 21:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2125 hrs on 18 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 18-Nov-2024 21:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120644PRICES SUBJECT TO REVIEW18/11/2024 09:20:23 PM

[EventId:202411182125_review] Prices for interval 18-Nov-2024 21:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2120 hrs on 18 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 18-Nov-2024 21:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120643PRICES SUBJECT TO REVIEW18/11/2024 09:15:24 PM

[EventId:202411182120_review] Prices for interval 18-Nov-2024 21:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2115 hrs on 18 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 18-Nov-2024 21:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120642PRICES SUBJECT TO REVIEW18/11/2024 09:10:15 PM

[EventId:202411182115_review] Prices for interval 18-Nov-2024 21:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2110 hrs on 18 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 18-Nov-2024 21:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120641PRICES SUBJECT TO REVIEW18/11/2024 09:05:15 PM

[EventId:202411182110_review] Prices for interval 18-Nov-2024 21:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2105 hrs on 18 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 18-Nov-2024 21:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120639PRICES SUBJECT TO REVIEW18/11/2024 09:00:20 PM

[EventId:202411182105_review] Prices for interval 18-Nov-2024 21:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2100 hrs on 18 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 18-Nov-2024 21:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120636MARKET INTERVENTION18/11/2024 06:24:54 PM

Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS

Refer to Market Notice 120609

Direction is cancelled from: 1830 hrs 18/11/2024

Manager NEM Real Time Operations
     
120626MARKET INTERVENTION18/11/2024 04:33:11 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 120553

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 20/11/2024.

The direction update is issued at 1630 hrs 18/11/2024.

Manager NEM Real Time Operations
     
120625MARKET INTERVENTION18/11/2024 04:37:54 PM

Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 120499


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1630 hrs 18/11/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0800 hrs 19/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 20/11/2024 / further notice.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm