Planned outage of the Red Cliffs - Wemen - Kerang 220kV line in the VIC region on 30/11/2024.
The Red Cliffs - Wemen - Kerang 220kV line in the Victorian (VIC) region is planned to be out of service from 0400 hrs to 1430 hrs on 30/11/2024.
A credible contingency event during this planned outage may require:
- Load shedding in the Victorian outer grid; and/ or
- Market intervention, such as the issuing of directions.
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO Operations
INC0138597 - RESOLVED - EMMS
SERVICE INTERRUPTION - SERVICE RESTORED
The Electricity Market Management System service has been restored.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
INC0138597 - ALERT - EMMS
AEMO is experiencing a service interruption relating to the Electricity Market Management System service.
AEMO is working on the issue and will provide updates as more information becomes available.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
Inter-Regional Transfer limit variation - Murraylink
Inter-Regional Transfer limit variation - Murraylink
There has been an unplanned outage of Murraylink.
The following constraint set was invoked at 1405 hrs 25/11/2024
I-ML_ZERO
The constraint set contains the following interconnector on the left hand side.
V-S-MNSP1
Refer to AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Directlink - NSW region - 22/11/2024
Inter-regional transfer limit variation - Directlink - NSW region - 22/11/2024
At 1911 hrs 22/11/2024 there was an unplanned outage of the No.2 leg of Directlink.
The following constraint set(s) invoked at 1920 hrs 22/11/2024
N-X_MBTE_2
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Directlink - NSW Region
Inter-Regional Transfer limit variation - Directlink - NSW Region
There has been an unplanned outage of the No 2 Leg of Directlink .
The following constraint set was invoked at 1720 hrs 22/11/2024
N-X_MBTE_2
The constraint set contains the following interconnector on the left hand side.
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
Network Augmentation Commissioned - QLD Region - 21/11/2024
Network Augmentation Commissioned - QLD Region - 21/11/2024
Commissioned:
Belmont No.2 275 kV 150 MVar reactor
Manager NEM Real Time Operations
Project Energy Connect (PEC-1) testing 21st November 2024 0600-0900 for flows in both directions
Refer to market notice 120307
There is an opportunity for testing Project Energy Connect (PEC-1) for flows in both directions up to 50 MW on 21st November from 06:00hrs to 09:00hrs
This test includes includes a fast runback of Murraylink.
Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.
Ben Blake
AEMO Operations
Inter-regional transfer limit variation - Moorabool - Sydenham No. 2 500 kV Line - VIC region - 19/11/2024
Inter-regional transfer limit variation - Moorabool - Sydenham No. 2 500 kV Line - VIC region - 19/11/2024
A planned outage of Moorabool - Sydenham No. 2 500 kV Line in the VIC region was scheduled from 1130 hrs 13/11/2024 to 1900 hrs 20/11/2024.
The outage has been completed and Moorabool - Sydenham No. 2 500 kV Line returned to service at 1640 hrs 19/11/2024
Constraint set(s) revoked: V-MLSY_NOEMTT_R