Market Notices

120885RESERVE NOTICE24/11/2024 03:19:15 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 24/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120858 is cancelled at 1515 hrs 24/11/2024.

Manager NEM Real Time Operations
     
120884RESERVE NOTICE24/11/2024 03:18:09 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 28/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period[s]:

[1.] From 1400 hrs 28/11/2024 to 1430 hrs 28/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1310 MW.

Manager NEM Real Time Operations
     
120883RESERVE NOTICE24/11/2024 03:17:04 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120861 has been updated at 1445 hrs 24/11/2024 to the following:

[1.] From 0830 hrs 27/11/2024 to 0930 hrs 27/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1298 MW.

[2.] From 2300 hrs 27/11/2024 to 0030 hrs 28/11/2024.
The forecast capacity reserve requirement is 1744 MW.
The minimum capacity reserve available is 1218 MW.

Manager NEM Real Time Operations
     
120882RESERVE NOTICE24/11/2024 03:13:39 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120860 has been updated at 1445 hrs 24/11/2024 to the following:

[1.] From 1330 hrs 26/11/2024 to 1400 hrs 26/11/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1233 MW.

[2.] From 2330 hrs 26/11/2024 to 0030 hrs 27/11/2024.
The forecast capacity reserve requirement is 1728 MW.
The minimum capacity reserve available is 1260 MW.

Manager NEM Real Time Operations
     
120878RESERVE NOTICE24/11/2024 01:04:40 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 25/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Periods:

[1.] From 1630 hrs 25/11/2024 to 1900 hrs 25/11/2024.
The forecast capacity reserve requirement is 1712 MW.
The minimum capacity reserve available is 1307 MW.

Manager NEM Real Time Operations
     
120872SETTLEMENTS RESIDUE23/11/2024 07:00:29 PM

[EventId:202411231900_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 23 November 2024 19:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1900 hrs on 23 November 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 23 November 2024.

Refer to market notice: 120871

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1900 hrs on 23 November 2024.

This is an AEMO autogenerated Market Notice.
     
120871SETTLEMENTS RESIDUE23/11/2024 06:40:22 PM

[EventId:202411231840_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 23 November 2024 18:40

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1840 hrs on 23 November 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 23 November 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1840 hrs on 23 November 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
120870SETTLEMENTS RESIDUE23/11/2024 06:15:20 PM

[EventId:202411231815_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 23 November 2024 18:15

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1815 hrs on 23 November 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 23 November 2024.

Refer to market notice: 120869

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1815 hrs on 23 November 2024.

This is an AEMO autogenerated Market Notice.
     
120869SETTLEMENTS RESIDUE23/11/2024 06:00:29 PM

[EventId:202411231800_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 23 November 2024 18:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1800 hrs on 23 November 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 23 November 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1800 hrs on 23 November 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm